6520-6522 N ROYER AVE 91307
Certificate Information: 6520-6522 N ROYER AVE 91307
- Application / Permit
- 21016-20000-03033
- Plan Check / Job No.
- B21VN01391
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT (405 SQ FT) PER LAMC 12.22 A. 33(c) and (e)
- Permit Issued
- Issued on 4/12/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 2/20/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/17/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/19/2021 | APPLICANT |
| Issued | 4/12/2021 | APPLICANT |
| CofO in Progress | 8/9/2021 | TROY SANDERS |
| CofO Issued | 8/10/2021 | JOHN JANSON |
| Permit Finaled | 8/10/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/4/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/16/2021 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 4/20/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 4/20/2021 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 5/18/2021 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 5/18/2021 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 5/18/2021 | Corrections Issued | TROY SANDERS |
| HVAC-Rough | 5/18/2021 | Approved | TROY SANDERS |
| Insulation | 5/18/2021 | Partial Approval | TROY SANDERS |
| Interior/Exterior Lathing | 5/18/2021 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 5/18/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 5/25/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 5/25/2021 | Approved | TROY SANDERS |
| Green Building Rough | 5/25/2021 | Approved | TROY SANDERS |
| Insulation | 5/25/2021 | Approved | TROY SANDERS |
| Drywall Nailing | 6/3/2021 | Corrections Issued | ASHLEY THOMPSON |
| Drywall Nailing | 6/14/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/14/2021 | Approved | RYAN SALAZAR |
| Final | 7/12/2021 | Corrections Issued | TROY SANDERS |
| Green Building Final | 7/12/2021 | Corrections Issued | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/12/2021 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 7/12/2021 | Approved | TROY SANDERS |
| Final | 8/9/2021 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 8/9/2021 | Approved | TROY SANDERS |