6520-6522 N ROYER AVE 91307

Certificate Information: 6520-6522 N ROYER AVE 91307

Application / Permit
21016-20000-03033
Plan Check / Job No.
B21VN01391
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT (405 SQ FT) PER LAMC 12.22 A. 33(c) and (e)  
Permit Issued
Issued on 4/12/2021
Issuing Office
Valley
Current Status
CofO Issued on 8/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 JEROME MAGAT PALMA
Corrections Issued 2/20/2021 JEROME MAGAT PALMA
Plan Check Approved 3/17/2021 JEROME MAGAT PALMA
Building Plans Picked Up 3/19/2021 APPLICANT
Issued 4/12/2021 APPLICANT
CofO in Progress 8/9/2021 TROY SANDERS
CofO Issued 8/10/2021 JOHN JANSON
Permit Finaled 8/10/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/4/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 3/4/2021 GABRIEL ROBLES
Sewer availability Cleared 3/4/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/16/2021 Approved TROY SANDERS
Footing/Foundation/Slab 4/20/2021 Approved TROY SANDERS
PLUMBING-Rough 4/20/2021 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 5/18/2021 Partial Approval TROY SANDERS
Drywall Nailing 5/18/2021 Partial Approval TROY SANDERS
ELECTRICAL-Rough 5/18/2021 Corrections Issued TROY SANDERS
HVAC-Rough 5/18/2021 Approved TROY SANDERS
Insulation 5/18/2021 Partial Approval TROY SANDERS
Interior/Exterior Lathing 5/18/2021 Partial Approval TROY SANDERS
PLUMBING-Rough 5/18/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 5/25/2021 Approved TROY SANDERS
ELECTRICAL-Rough 5/25/2021 Approved TROY SANDERS
Green Building Rough 5/25/2021 Approved TROY SANDERS
Insulation 5/25/2021 Approved TROY SANDERS
Drywall Nailing 6/3/2021 Corrections Issued ASHLEY THOMPSON
Drywall Nailing 6/14/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 6/14/2021 Approved RYAN SALAZAR
Final 7/12/2021 Corrections Issued TROY SANDERS
Green Building Final 7/12/2021 Corrections Issued TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Approved TROY SANDERS
Smoke Detectors 7/12/2021 Approved TROY SANDERS
Final 8/9/2021 OK to Issue CofO TROY SANDERS
Green Building Final 8/9/2021 Approved TROY SANDERS