7253-7255 N CLAIRE AVE 91335

Certificate Information: 7253-7255 N CLAIRE AVE 91335

Application / Permit
21016-20000-02836
Plan Check / Job No.
B21VN01295
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT (378 SQ FT) PER LAMC 12.22 A. 33(c) and (e)  
Permit Issued
Issued on 4/15/2021
Issuing Office
Current Status
CofO Issued on 8/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2021 APPLICANT
Assigned to Plan Check Engineer 2/16/2021 SARKIS HARABEDIAN
Corrections Issued 2/17/2021 SARKIS HARABEDIAN
Plan Check Approved 3/19/2021 JEROME MAGAT PALMA
Building Plans Picked Up 3/24/2021 APPLICANT
Issued 4/15/2021 APPLICANT
CofO in Progress 8/13/2021 VINCENT HANLEY
Permit Finaled 8/13/2021 JOHN JANSON
CofO Issued 8/13/2021 JOHN JANSON
Permit Finaled 8/13/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/2/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/2/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/2/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/22/2021 Approved VINCENT HANLEY
PLUMBING-Rough 4/22/2021 Partial Approval VINCENT HANLEY
Sewer 4/22/2021 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 4/26/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 5/4/2021 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 5/4/2021 Approved VINCENT HANLEY
Wood Frame 5/4/2021 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 5/14/2021 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 5/14/2021 Approved JEFFREY PARD
Green Building Rough 5/14/2021 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 5/19/2021 Partial Approval VINCENT HANLEY
Green Building Rough 5/19/2021 Approved VINCENT HANLEY
Insulation 5/19/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/19/2021 Partial Approval VINCENT HANLEY
Drywall Nailing 5/24/2021 Corrections Issued DEANDRE HOFFMAN
BUILDING-Rough-Frame 5/25/2021 Approved SHAVONNE ESPINOZA
Drywall Nailing 5/25/2021 Approved SHAVONNE ESPINOZA
Interior/Exterior Lathing 5/28/2021 Approved JESUS RODRIGUEZ
Shower Pan 6/3/2021 Approved DAVID SCANTLIN
Final 7/29/2021 Corrections Issued MICHAEL PELHAM
Green Building Final 7/29/2021 Approved MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 7/29/2021 SGSOV Not Ready MICHAEL PELHAM
Smoke Detectors 7/29/2021 Corrections Issued MICHAEL PELHAM
Final 8/3/2021 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/3/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 8/3/2021 Approved VINCENT HANLEY
Final 8/13/2021 OK to Issue CofO VINCENT HANLEY