8601 N MOREHART AVE 91352

Certificate Information: 8601 N MOREHART AVE 91352

Application / Permit
21016-20000-02589
Plan Check / Job No.
B21VN01221
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO ENLARGE/REMODEL BATHROOM AND CONVERT LIVING ROOM TO NEW BEDROOM. ADD NEW WINDOWS AND DOORS. REMOVE (E) MASONRY CHIMNEY AND REPAIR (E) CHIMNEY FOUNDATION.
Permit Issued
Issued on 2/18/2021
Issuing Office
Current Status
Permit Finaled on 11/1/2021

Permit Application Status History

Submitted 2/1/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 JEROME MAGAT PALMA
Plan Check Approved 2/15/2021 JEROME MAGAT PALMA
Plan Check Approved 2/18/2021 JEROME MAGAT PALMA
Issued 2/18/2021 APPLICANT
Permit Finaled 11/1/2021 CHRISTOPHER DELLEFIELD

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/6/2021 Conditional Approval JOHN HAYES
Footing/Foundation/Slab 5/14/2021 Approved JOHN HAYES
BUILDING-Rough-Frame 6/9/2021 Corrections Issued JOHN HAYES
Rough-Elec/Plmb/HVAC 6/9/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 6/15/2021 Partial Approval JOHN HAYES
ELECTRICAL-Rough 6/15/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 6/21/2021 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 6/21/2021 Approved JOHN HAYES
Insulation 6/24/2021 Approved MATTHEW NELSON
Drywall Nailing 6/29/2021 Approved DEANDRE HOFFMAN
Pre-Inspection 7/15/2021 Partial Inspection CALEB MEISTER
Shower Pan 7/15/2021 Corrections Issued ASHLEY THOMPSON
Shower Pan 7/19/2021 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 7/21/2021 Approved ALAN MORELOS
Final 9/9/2021 Corrections Issued JOHN HAYES
SGSOV-Seismic Gas S/O Valve 9/9/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 9/9/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 10/28/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Final 10/28/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 10/28/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 10/28/2021 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 10/28/2021 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 10/28/2021 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 11/1/2021 Approved CHRISTOPHER DELLEFIELD
Final 11/1/2021 Permit Finaled CHRISTOPHER DELLEFIELD
Smoke Detectors 11/1/2021 Approved CHRISTOPHER DELLEFIELD