10205 W WOODBINE ST 90034

Certificate Information: 10205 W WOODBINE ST 90034

Application / Permit
21016-20000-02375
Plan Check / Job No.
B21VN01119
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT (E) 31' 1" X 18' 6" PORTION OF ATTACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(C). ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 8/5/2021
Issuing Office
Current Status
CofO Issued on 9/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 GURUNATH NESARAJAH
Corrections Issued 2/15/2021 GURUNATH NESARAJAH
Plan Check Approved 6/21/2021 GURUNATH NESARAJAH
Building Plans Picked Up 6/23/2021 APPLICANT
Issued 8/5/2021 APPLICANT
CofO in Progress 9/1/2022 SORIN CIRSTOIU
CofO in Progress 9/1/2022 SORIN CIRSTOIU
Permit Finaled 9/6/2022 DAVID TSAU
CofO Issued 9/6/2022 DAVID TSAU
Permit Finaled 9/6/2022 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 3/10/2021 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 3/10/2021 TRACY TATE
Sewer availability Cleared 3/16/2021 TRACY TATE
ZA Case Cleared 4/12/2021 STEVEN WECHSLER
ZI Cleared 4/12/2021 STEVEN WECHSLER
Specific Plan Cleared 4/13/2021 DYLAN SITTIG
Fire Marshal Fire Life Safety Cleared 5/11/2021 ANDREW KO
Specific Plan Cleared 6/9/2021 VALERIA CEJA
Construction near power lines Cleared 6/10/2021 RIDWAN HARDY

Contact Information

Contractor Dh Remodel Services; Lic. No.: 1030925-B 5850 W 3RD STREET #160      LOS ANGELES, CA 90036
Engineer Zohrevand,, Pedram; Lic. No.: C82328 19562 VENTURA BLVD UNIT 238      TARZANA, CA 91356

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/25/2021 Partial Inspection PAUL DAVIDSON
Deputy Drilled-In Anchors 10/26/2021 Approved NICK LAROCCA
Excavation/Setback/Form/Re-Bar 10/28/2021 Approved NICK LAROCCA
Footing/Foundation/Slab 10/28/2021 Approved NICK LAROCCA
Green Building Rough 4/22/2022 Not Ready for Inspection PAUL DAVIDSON
Wood Frame 4/22/2022 Not Ready for Inspection PAUL DAVIDSON
Reinforced Concrete Frame 5/23/2022 Partial Inspection JOHN DODGE
Drywall Nailing 5/27/2022 Partial Approval JOHN DODGE
Green Building Rough 5/27/2022 Approved JOHN DODGE
Wood Frame 6/3/2022 Approved PAUL DAVIDSON
Interior/Exterior Lathing 6/8/2022 Partial Approval PAUL DAVIDSON
Insulation 6/10/2022 Approved SORIN CIRSTOIU
Drywall Nailing 6/24/2022 Approved PAUL DAVIDSON
Interior/Exterior Lathing 6/24/2022 Approved PAUL DAVIDSON
Final 8/18/2022 Not Ready for Inspection SORIN CIRSTOIU
Green Building Final 8/18/2022 Not Ready for Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 8/18/2022 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 8/18/2022 Not Ready for Inspection SORIN CIRSTOIU
Final 8/24/2022 Not Ready for Inspection SORIN CIRSTOIU
Green Building Final 8/24/2022 Not Ready for Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 8/24/2022 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 8/24/2022 Not Ready for Inspection SORIN CIRSTOIU
Final 9/1/2022 OK to Issue CofO SORIN CIRSTOIU
Green Building Final 9/1/2022 Approved SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 9/1/2022 SGSOV Approved SORIN CIRSTOIU
Smoke Detectors 9/1/2022 Approved SORIN CIRSTOIU