14715 W COLLINS ST 91411

Certificate Information: 14715 W COLLINS ST 91411

Application / Permit
21016-20000-02147
Plan Check / Job No.
B21VN01044
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO ADU - 1 OF 3
Permit Issued
Issued on 10/10/2021
Issuing Office
Current Status
CofO Issued on 8/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 SELLA BENYAMIN
Corrections Issued 2/25/2021 SELLA BENYAMIN
Quality Review Completed 2/26/2021 STEVEN KIM
Building Plans Picked Up 2/26/2021 APPLICANT
Plan Check Approved 10/8/2021 SELLA BENYAMIN
Issued 10/10/2021 APPLICANT
CofO in Progress 8/3/2022 RICHARD DOCKUS
Permit Finaled 8/26/2022 DANIEL ORRANTE
Permit Finaled 8/26/2022 DANIEL ORRANTE
CofO Issued 8/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/1/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 3/1/2021 GUILLERMO PETRA
Sewer availability Cleared 3/1/2021 GUILLERMO PETRA
Construction near power lines Cleared 5/4/2021 RIDWAN HARDY
Public Works-Sewers Cleared 8/3/2022 DAGOVERTO GUERRERO

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor America Green Builders; Lic. No.: 1020657-B 6601 ALCOVE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/27/2021 Approved RICHARD DOCKUS
Footing/Foundation/Slab 1/20/2022 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 1/24/2022 Approved RICHARD DOCKUS
Footing/Foundation/Slab 1/31/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/22/2022 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 2/22/2022 Partial Approval RICHARD DOCKUS
Green Building Rough 2/22/2022 Not Ready for Inspection RICHARD DOCKUS
Underground Mechanical 2/22/2022 Partial Approval RICHARD DOCKUS
Wood Frame 2/22/2022 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 3/21/2022 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Rough 3/21/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Rough 3/21/2022 Approved RICHARD DOCKUS
HVAC-Rough 3/21/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 3/21/2022 Corrections Issued RICHARD DOCKUS
Underground Mechanical 3/21/2022 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 3/25/2022 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 3/25/2022 Approved RICHARD DOCKUS
HVAC-Rough 3/25/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 3/25/2022 Approved RICHARD DOCKUS
Deputy Wood Construction 3/29/2022 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 3/31/2022 Approved RICHARD DOCKUS
HVAC-Rough 3/31/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 4/4/2022 Partial Approval ALAN MORELOS
Insulation 4/7/2022 Approved ALAN MORELOS
Drywall Nailing 4/14/2022 Corrections Issued ALAN MORELOS
Drywall Nailing 4/20/2022 Approved RICHARD DOCKUS
Final 7/12/2022 Corrections Issued RICHARD DOCKUS
Green Building Final 7/12/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 7/12/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 7/12/2022 Approved RICHARD DOCKUS
Final 8/2/2022 OK to Issue CofO RICHARD DOCKUS