10614 N PLAINVIEW AVE 91042
Certificate Information: 10614 N PLAINVIEW AVE 91042
- Application / Permit
- 21016-20000-02038
- Plan Check / Job No.
- B21VN00966
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 19' X 24' DETACHED RECREATION ROOM TO ACCESSORY DWELLING UNIT AS PER GCS 65852.2(E)(1)(B), NFPA-13D FIRE SPRINKLERS REQUIRED THOURGHOUT , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/29/2021
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | RARES BODEA |
| Corrections Issued | 2/25/2021 | RARES BODEA |
| Quality Review Completed | 3/4/2021 | STEVEN KIM |
| Building Plans Picked Up | 3/5/2021 | APPLICANT |
| Applicant returned to address corrections | 7/21/2021 | RARES BODEA |
| Plan Check Approved | 11/29/2021 | RARES BODEA |
| Issued | 11/29/2021 | APPLICANT |
| CofO in Progress | 11/28/2023 | WILLIAM WREN |
| No Progress | 11/28/2023 | WILLIAM WREN |
| CofO in Progress | 11/28/2023 | WILLIAM WREN |
| CofO in Progress | 3/11/2024 | WILLIAM WREN |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
| CofO Issued | 3/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/16/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/16/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 10/13/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 10/14/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng David; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/5/2023 | Partial Inspection | WILLIAM WREN |
| Pre-Inspection | 6/28/2023 | Partial Inspection | WILLIAM WREN |
| Footing/Foundation/Slab | 7/7/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/22/2023 | Corrections Issued | WILLIAM WREN |
| HVAC-Rough | 8/22/2023 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 8/22/2023 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 10/4/2023 | Approved | WILLIAM WREN |
| Green Building Rough | 10/4/2023 | Approved | WILLIAM WREN |
| Rough-Elec/Plmb/HVAC | 10/4/2023 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 10/4/2023 | Approved | WILLIAM WREN |
| Insulation | 10/16/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 11/2/2023 | Approved | DAVID MATSON |
| Final | 11/7/2023 | Not Ready for Inspection | WILLIAM WREN |
| Green Building Final | 11/7/2023 | Approved | WILLIAM WREN |
| Service/Power Release | 11/7/2023 | Approved | WILLIAM WREN |
| Final | 2/28/2024 | Corrections Issued | WILLIAM WREN |
| Final | 3/11/2024 | OK to Issue CofO | WILLIAM WREN |