8957-8959 N DEBRA AVE 91343
Certificate Information: 8957-8959 N DEBRA AVE 91343
- Application / Permit
- 21016-20000-01911
- Plan Check / Job No.
- B21VN00895
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 20' X 20' ATTACHED GARAGE AND 12' X 13' PORTION OF (E) SFD TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A); REMOVE PORTION OF (E) WALL AT FAMILY ROOM AND REMODEL (E) BEDROOMS/CLOSET/BATHROOMS, REMOVE AND REPLACE ALL WINDOWS (SAME SIZE, SAME LOCATION). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/10/2021
- Issuing Office
- Current Status
- CofO Issued on 11/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2021 | JENNIFER LEE |
| Corrections Issued | 2/10/2021 | JENNIFER LEE |
| Plan Check Approved | 3/22/2021 | JENNIFER LEE |
| Building Plans Picked Up | 3/24/2021 | APPLICANT |
| Issued | 4/10/2021 | APPLICANT |
| CofO in Progress | 9/22/2021 | JACK KARGODORIAN |
| Permit Finaled | 11/30/2021 | MICHAEL SMITH |
| CofO Issued | 11/30/2021 | MICHAEL SMITH |
| Permit Finaled | 11/30/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/18/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2021 | LEE GUILBEAUX |
| Permit | Cleared | 2/18/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/18/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Leapfrog Enterprises Inc; Lic. No.: 714459-B | 1593 EDMUND STREET SIMI VALLEY, CA 93065 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/7/2021 | Conditional Approval | MICHAEL TEMPLE |
| Underground Mechanical | 5/11/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 5/12/2021 | Approved | ARTHUR SARGSYAN |
| Underground Mechanical | 5/12/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 6/14/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 6/14/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 6/14/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 6/14/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 6/14/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 6/17/2021 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/23/2021 | Approved | JUSTIN HAWLEY |
| Shower Pan | 6/23/2021 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 6/24/2021 | Approved | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/29/2021 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 9/1/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 9/1/2021 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 9/1/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Final | 9/1/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Final | 9/1/2021 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/1/2021 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 9/1/2021 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 9/13/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 9/13/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 9/13/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 9/13/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 9/13/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 9/16/2021 | Approved | JENNIFER RABUCHIN |
| Final | 9/16/2021 | OK to Issue CofO | JENNIFER RABUCHIN |