11865 W BRAY ST 90230
Certificate Information: 11865 W BRAY ST 90230
- Application / Permit
- 21016-20000-01903
- Plan Check / Job No.
- B21VN00884
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE WALL BETWEEN KITCHEN & LIVING ROOM AND REMODEL KITCHEN OF (E) SFD. ALL WORK PER DESIGN.
- Permit Issued
- Issued on 3/9/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/8/2021
Permit Application Status History
| Submitted | 1/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2021 | RAPHAEL ROSAS |
| Corrections Issued | 2/6/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/23/2021 | RAPHAEL ROSAS |
| Issued | 3/9/2021 | APPLICANT |
| Building Plans Picked Up | 3/10/2021 | APPLICANT |
| Permit Finaled | 6/7/2021 | JOHNNY MIRANDA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Butel Construction Inc; Lic. No.: 852273-B | 257 SOUTH CITRUS AVE LOS ANGELES, CA 90036 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/19/2021 | Partial Approval | DAVID HEINE |
| ELECTRICAL-Rough | 3/31/2021 | Not Ready for Inspection | PIERRE VEGA |
| HVAC-Rough | 3/31/2021 | Not Ready for Inspection | PIERRE VEGA |
| PLUMBING-Rough | 3/31/2021 | Not Ready for Inspection | PIERRE VEGA |
| Wood Frame | 3/31/2021 | Corrections Issued | PIERRE VEGA |
| BUILDING-Rough-Frame | 4/5/2021 | Approved | PIERRE VEGA |
| MERV13>=Rough | 4/5/2021 | Approved | PIERRE VEGA |
| Rough-Elec/Plmb/HVAC | 4/5/2021 | Approved | PIERRE VEGA |
| Drywall Nailing | 4/6/2021 | Not Ready for Inspection | PIERRE VEGA |
| ELECTRICAL-Rough | 4/6/2021 | Approved | PIERRE VEGA |
| HVAC-Rough | 4/6/2021 | Approved | PIERRE VEGA |
| Insulation | 4/6/2021 | Approved | PIERRE VEGA |
| PLUMBING-Rough | 4/6/2021 | Approved | PIERRE VEGA |
| Drywall Nailing | 4/8/2021 | Conditional Approval | KENNETH NAGLE |
| Interior/Exterior Lathing | 4/20/2021 | Approved | PIERRE VEGA |
| ELECTRICAL-Final | 6/7/2021 | Approved | JOHNNY MIRANDA |
| Final | 6/7/2021 | Permit Finaled | JOHNNY MIRANDA |
| HVAC-Final | 6/7/2021 | Approved | JOHNNY MIRANDA |
| MERV13>=Final | 6/7/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 6/7/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 6/7/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 6/7/2021 | Approved | JOHNNY MIRANDA |