2536 S BUNDY DR 90064
Certificate Information: 2536 S BUNDY DR 90064
- Application / Permit
- 21016-20000-01847
- Plan Check / Job No.
- B21VN00839
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 21'-0" X 28'-0'' IRREGULAR SHAPED 2-STORY (E) RECREATION ROOM, STORAGE AND CARPORT INTO A (N) DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2021 | RAPHAEL ROSAS |
| Corrections Issued | 2/6/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 4/9/2021 | APPLICANT |
| Applicant returned to address corrections | 7/20/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 5/29/2024 | GIOVANNY CHAVEZ |
| Issued | 6/3/2024 | APPLICANT |
| CofO Issued | 12/28/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/28/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 9/14/2022 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 12/19/2022 | PEDRO AYALA |
| Construction near power lines | Cleared | 2/17/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lao,, Arturo Begino; Lic. No.: C56687 | 16348 MIDWOOD DR GRANADA HILLS, CA 91344 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/12/2024 | Partial Inspection | HERBERT GIRON |
| Underground Mechanical | 6/27/2024 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 7/2/2024 | Approved | JESUS PINEDA |
| Sewer | 7/8/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/10/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 7/10/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 7/10/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 7/10/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 7/18/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 7/18/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 7/18/2024 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 8/12/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 8/12/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 8/12/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 8/12/2024 | Approved | JESUS PINEDA |
| MERV13>=Rough | 8/12/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 8/12/2024 | Approved | JESUS PINEDA |
| Wood Frame | 8/12/2024 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 8/21/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 9/4/2024 | Approved | REGINA MENDEZ |
| Final | 9/19/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 9/19/2024 | Not Ready for Inspection | KIRK SANDERS |
| MERV13>=Final | 9/19/2024 | Approved | KIRK SANDERS |
| Smoke Detectors | 9/19/2024 | Corrections Issued | KIRK SANDERS |
| Final | 9/23/2024 | Partial Approval | DANIEL VERA |
| Green Building Final | 9/23/2024 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 9/23/2024 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 9/23/2024 | Approved | DANIEL VERA |
| Final | 12/24/2024 | OK to Issue CofO | DANIEL VERA |