6241 N CARPENTER AVE 91606

Certificate Information: 6241 N CARPENTER AVE 91606

Application / Permit
21016-20000-01794
Plan Check / Job No.
B21VN00828
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 18' X 20' (E) DETACHED GARAGE AND 13' X 18' STORAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 4/19/2021
Issuing Office
Current Status
CofO Issued on 5/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 RAPHAEL ROSAS
Corrections Issued 2/15/2021 RAPHAEL ROSAS
Plan Check Approved 3/17/2021 RAPHAEL ROSAS
Issued 4/19/2021 APPLICANT
CofO in Progress 5/10/2022 MISAEL ESPARZA
CofO Issued 5/10/2022 MICHAEL SMITH
Permit Finaled 5/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/17/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 2/17/2021 GABRIEL ROBLES
Sewer availability Cleared 2/17/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/3/2021 Not Ready for Inspection DANIEL DREW
Pre-Inspection 5/3/2021 Approved DANIEL DREW
Sewer 5/3/2021 Corrections Issued DANIEL DREW
Sewer 5/24/2021 Not Ready for Inspection THOMAS FINNILA
Deputy Drilled-In Anchors 6/7/2021 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 6/9/2021 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 6/9/2021 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 6/21/2021 Partial Approval CHRISTOPHE COCHRAN
Wood Frame 6/21/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/24/2021 Approved DANIEL DREW
Sewer 6/24/2021 Approved DANIEL DREW
Underground Mechanical 6/24/2021 Partial Approval DANIEL DREW
BUILDING-Rough-Frame 9/9/2021 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Rough 9/9/2021 Approved DANIEL DREW
Footing/Foundation/Slab 9/9/2021 Approved DANIEL DREW
Green Building Rough 9/9/2021 Not Ready for Inspection DANIEL DREW
PLUMBING-Rough 9/29/2021 Corrections Issued LILIANA PORTILLO
Gas Test 10/1/2021 Approved LILIANA PORTILLO
Insulation 10/1/2021 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 10/1/2021 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/5/2021 Partial Inspection MICHEL ABAJAN
Green Building Rough 10/5/2021 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 10/12/2021 No Access for Inspection CHRISTOPHER DELLEFIELD
Green Building Rough 10/12/2021 No Access for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 10/20/2021 Corrections Issued DANIEL DREW
Green Building Rough 10/20/2021 Not Ready for Inspection DANIEL DREW
HVAC-Rough 10/20/2021 Approved DANIEL DREW
Interior/Exterior Lathing 10/25/2021 Not Ready for Inspection CALEB MEISTER
Wood Frame 10/29/2021 Partial Approval ARAM AVEDISIAN
Insulation 11/4/2021 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 11/4/2021 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 11/4/2021 Not Ready for Inspection MISAEL ESPARZA
Insulation 11/9/2021 Corrections Issued MATT KELLERMAN
Interior/Exterior Lathing 11/9/2021 Not Ready for Inspection MATT KELLERMAN
Wood Frame 11/9/2021 Not Ready for Inspection MATT KELLERMAN
Insulation 11/19/2021 Not Ready for Inspection DANIEL DREW
Wood Frame 11/19/2021 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Rough 12/9/2021 Corrections Issued ARAM AVEDISIAN
Insulation 12/9/2021 Not Ready for Inspection ARAM AVEDISIAN
Wood Frame 12/9/2021 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 12/23/2021 Partial Approval ARAM AVEDISIAN
Wood Frame 12/23/2021 Not Ready for Inspection ARAM AVEDISIAN
Interior/Exterior Lathing 12/30/2021 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/5/2022 Corrections Issued CALEB MEISTER
Green Building Rough 1/5/2022 Approved CALEB MEISTER
BUILDING-Rough-Frame 1/19/2022 Approved CALEB MEISTER
Insulation 1/19/2022 Approved CALEB MEISTER
Drywall Nailing 2/2/2022 Approved CHRISTOPHE COCHRAN
Final 2/9/2022 Corrections Issued CALEB MEISTER
Interior/Exterior Lathing 2/9/2022 Approved CALEB MEISTER
Final 2/22/2022 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 2/22/2022 SGSOV Not Ready THOMAS FINNILA
Final 3/3/2022 Corrections Issued CHRISTOPHE COCHRAN
Final 4/8/2022 Corrections Issued MATT KELLERMAN
Green Building Final 4/8/2022 Corrections Issued MATT KELLERMAN
SGSOV-Seismic Gas S/O Valve 4/8/2022 SGSOV Approved MATT KELLERMAN
Smoke Detectors 4/8/2022 Approved MATT KELLERMAN
Final 4/25/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 4/25/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 5/3/2022 Corrections Issued ARAM AVEDISIAN
Final 5/9/2022 OK to Issue CofO MISAEL ESPARZA
Green Building Final 5/9/2022 Approved MISAEL ESPARZA