13603 N FELLOWS AVE 91342
Certificate Information: 13603 N FELLOWS AVE 91342
- Application / Permit
- 21016-20000-01770
- Plan Check / Job No.
- B21VN00817
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED 17' 6" X 23' RECREATION ROOM AND STORAGE TO NEW ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 5/26/2021
- Issuing Office
- Current Status
- CofO Issued on 4/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 2/13/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 5/25/2021 | GURUNATH NESARAJAH |
| Issued | 5/26/2021 | APPLICANT |
| Building Plans Picked Up | 6/3/2021 | APPLICANT |
| CofO in Progress | 3/13/2026 | KEVIN BERBERYAN |
| Permit Finaled | 4/2/2026 | RUBEN SALAS |
| CofO Issued | 4/2/2026 | RUBEN SALAS |
| Permit Finaled | 4/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/18/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/18/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2021 | JOHN TRIANTAFYLLOS |
| ZA Case | Cleared | 5/6/2021 | DANG NGUYEN |
| ZI | Cleared | 5/13/2021 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/21/2025 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/21/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 4/21/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 6/6/2025 | Approved | KEVIN BERBERYAN |
| Gas Test | 6/6/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 6/6/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 6/6/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 6/6/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/4/2025 | Approved | KEVIN BERBERYAN |
| Final | 9/4/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 9/4/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Rough | 9/4/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 9/4/2025 | Approved | KEVIN BERBERYAN |
| Final | 3/10/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Final | 3/10/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 3/13/2026 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 3/13/2026 | Approved | KEVIN BERBERYAN |