711 1/2 N MCCADDEN PL 90038
Certificate Information: 711 1/2 N MCCADDEN PL 90038
- Application / Permit
- 21016-20000-01734
- Plan Check / Job No.
- B21VN00793
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 35'-1" X 15'-6" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (952 SQ FT) PER LAMC 12.22 A. 33(c) and (d)
- Permit Issued
- Issued on 1/31/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 2/9/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 7/21/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/18/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
| Issued | 1/31/2025 | APPLICANT |
| CofO in Progress | 10/23/2025 | CRAIG VAUGHAN |
| Permit Finaled | 10/25/2025 | DEROLD HAUFF |
| CofO Issued | 10/25/2025 | DEROLD HAUFF |
| Permit Finaled | 10/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/27/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2021 | CELINA MORENO |
| Sewer availability | Cleared | 5/27/2021 | CELINA MORENO |
| Low Impact Development | Cleared | 3/3/2022 | ROGELIO CORTES |
Contact Information
| Contractor | Sns Realty Inc; Lic. No.: 1113238-B | 822 N MCCADDEN PL LOS ANGELES, CA 90038 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/3/2025 | Partial Inspection | WILLIAM SIERRA |
| Pre-Inspection | 2/6/2025 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 3/13/2025 | Partial Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 3/26/2025 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/11/2025 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/17/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/21/2025 | Corrections Issued | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 4/23/2025 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 5/30/2025 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/30/2025 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/16/2025 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/16/2025 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 6/16/2025 | Approved | CRAIG VAUGHAN |
| METHANE-Rough | 6/16/2025 | Approved | CRAIG VAUGHAN |
| Insulation | 6/23/2025 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 6/23/2025 | Partial Approval | BRIAN SULLIVAN |
| Drywall Nailing | 6/26/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 6/26/2025 | Approved | JOSH MEISTER |
| Underground Mechanical | 6/30/2025 | Partial Approval | JOSH MEISTER |
| Underground Mechanical | 7/3/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Underground Mechanical | 7/7/2025 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/30/2025 | Approved | CRAIG VAUGHAN |
| Final | 9/30/2025 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/30/2025 | Approved | CRAIG VAUGHAN |
| Green Building Final | 9/30/2025 | Approved | CRAIG VAUGHAN |
| METHANE-Barrier | 9/30/2025 | Approved | CRAIG VAUGHAN |
| METHANE-Subgrade | 9/30/2025 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 9/30/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 9/30/2025 | Approved | CRAIG VAUGHAN |
| Final | 10/3/2025 | Corrections Issued | CRAIG VAUGHAN |
| Service/Power Release | 10/3/2025 | Approved | CRAIG VAUGHAN |
| Final | 10/17/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 10/20/2025 | Corrections Issued | CRAIG VAUGHAN |
| Final | 10/22/2025 | OK to Issue CofO | CRAIG VAUGHAN |