6048 N WILLOW CREST AVE 91606

Certificate Information: 6048 N WILLOW CREST AVE 91606

Application / Permit
21016-20000-01467
Plan Check / Job No.
B21VN00652
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' 4" X 18' 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 10/6/2021
Issuing Office
Current Status
CofO Issued on 9/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2021 APPLICANT
Assigned to Plan Check Engineer 2/25/2021 GURUNATH NESARAJAH
Corrections Issued 2/27/2021 GURUNATH NESARAJAH
Plan Check Approved 6/17/2021 GURUNATH NESARAJAH
Building Plans Picked Up 6/23/2021 APPLICANT
Issued 10/6/2021 APPLICANT
CofO in Progress 8/20/2024 ROBERTO PALACIOS-LOPEZ
Permit Finaled 9/4/2024 DANIEL ORRANTE
CofO Issued 9/4/2024 DANIEL ORRANTE
Permit Finaled 9/4/2024 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 5/5/2021 RIDWAN HARDY
Address approval Cleared 5/17/2021 ADRIAN CASTRO
Sewer availability Cleared 5/17/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/3/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/14/2022 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 3/25/2022 Partial Approval DAVID MATSON
Footing/Foundation/Slab 3/25/2022 Partial Inspection DAVID MATSON
PLUMBING-Rough 4/15/2022 Corrections Issued CALEB MEISTER
PLUMBING-Rough 4/21/2022 Partial Approval CALEB MEISTER
Sewer 4/21/2022 Not Ready for Inspection CALEB MEISTER
Footing/Foundation/Slab 5/13/2022 Approved ARAM AVEDISIAN
Sewer 6/28/2022 Partial Approval CALEB MEISTER
ELECTRICAL-Rough 9/12/2022 Corrections Issued CALEB MEISTER
HVAC-Rough 9/12/2022 Corrections Issued CALEB MEISTER
PLUMBING-Rough 9/12/2022 Corrections Issued CALEB MEISTER
BUILDING-Rough-Frame 10/28/2022 No Access for Inspection JOHN HAYES
ELECTRICAL-Rough 10/28/2022 No Access for Inspection JOHN HAYES
Green Building Rough 10/28/2022 No Access for Inspection JOHN HAYES
HVAC-Rough 10/28/2022 No Access for Inspection JOHN HAYES
PLUMBING-Rough 10/28/2022 No Access for Inspection JOHN HAYES
BUILDING-Rough-Frame 11/8/2022 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 11/8/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 11/8/2022 Not Ready for Inspection JOHN HAYES
HVAC-Rough 11/8/2022 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 11/8/2022 Partial Approval JOHN HAYES
PLUMBING-Rough 11/8/2022 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 2/21/2023 Not Ready for Inspection JOHN HAYES
Green Building Rough 2/21/2023 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 2/21/2023 Corrections Issued JOHN HAYES
Underground Mechanical 2/21/2023 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 4/4/2023 Approved JOHN HAYES
ELECTRICAL-Rough 4/4/2023 Approved JOHN HAYES
Green Building Rough 4/4/2023 Approved JOHN HAYES
HVAC-Rough 4/4/2023 Approved JOHN HAYES
PLUMBING-Rough 4/4/2023 Approved JOHN HAYES
Insulation 4/18/2023 Conditional Approval JOHN COLEMAN
Shower Pan 4/18/2023 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/16/2023 Corrections Issued ROBERT GOLD
Deputy Wood Construction 5/18/2023 Conditional Approval MICHAEL SMITH
Drywall Nailing 5/31/2023 Approved JOHN HAYES
Interior/Exterior Lathing 5/31/2023 Not Ready for Inspection JOHN HAYES
Drywall Nailing 6/1/2023 Approved JOHN HAYES
Interior/Exterior Lathing 6/8/2023 Approved JOHN HAYES
Sewer 6/27/2023 Approved JOHN HAYES
ELECTRICAL-Final 12/7/2023 Approved JOHN HAYES
Final 12/7/2023 Corrections Issued JOHN HAYES
Green Building Final 12/7/2023 Approved JOHN HAYES
HVAC-Final 12/7/2023 Approved JOHN HAYES
PLUMBING-Final 12/7/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 12/7/2023 SGSOV Approved JOHN HAYES
Smoke Detectors 12/7/2023 Approved JOHN HAYES
Final 4/15/2024 Not Ready for Inspection JENNIFER RABUCHIN
Service/Power Release 4/15/2024 Corrections Issued JENNIFER RABUCHIN
Final 8/19/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ