1613 N AVENUE 46 90041

Certificate Information: 1613 N AVENUE 46 90041

Application / Permit
21016-20000-01396
Plan Check / Job No.
B21VN00629
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (354 SQ FT) PER LAMC 12.22 A. 33(c) and (d)
Permit Issued
Issued on 6/2/2021
Issuing Office
Current Status
CofO Issued on 3/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Building Plans Picked Up 4/7/2020 APPLICANT
Submitted 1/28/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 JEROME MAGAT PALMA
Corrections Issued 2/15/2021 JEROME MAGAT PALMA
Plan Check Approved 4/1/2021 JEROME MAGAT PALMA
Issued 6/2/2021 APPLICANT
CofO in Progress 3/8/2023 CRAIG VAUGHAN
Permit Finaled 3/15/2023 DEROLD HAUFF
CofO Issued 3/15/2023 DEROLD HAUFF
Permit Finaled 3/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/4/2021 CECILIO NAVARRO
Sewer availability Cleared 3/4/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 3/10/2021 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/16/2021 No Access for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 9/27/2021 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 9/30/2021 Approved CRAIG VAUGHAN
Underground Mechanical 9/30/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 10/6/2021 Partial Approval CRAIG VAUGHAN
Special/Order Compliance 10/12/2021 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 11/5/2021 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/5/2021 Partial Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 2/10/2022 Approved CRAIG VAUGHAN
Green Building Rough 2/10/2022 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 2/10/2022 Partial Approval CRAIG VAUGHAN
Insulation 2/18/2022 Approved CRAIG VAUGHAN
Shower Pan 2/18/2022 Approved CRAIG VAUGHAN
Drywall Nailing 3/4/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/4/2022 Approved CRAIG VAUGHAN
Final 6/30/2022 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 6/30/2022 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Not Ready KATHRYN BUTTERWORTH
Smoke Detectors 6/30/2022 Approved KATHRYN BUTTERWORTH
Final 7/12/2022 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/12/2022 SGSOV Approved CRAIG VAUGHAN
ELECTRICAL-Final 3/7/2023 Approved CRAIG VAUGHAN
Final 3/7/2023 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 3/7/2023 Approved CRAIG VAUGHAN
PLUMBING-Final 3/7/2023 Approved CRAIG VAUGHAN