3753 W 60TH ST 90043
Certificate Information: 3753 W 60TH ST 90043
- Application / Permit
- 21016-20000-01395
- Plan Check / Job No.
- B21VN00628
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 30' X 20' 5" DETACHED GARAGE/STORAGE TO ADU PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 1/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 2/6/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 3/8/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 11/2/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 11/5/2021 | APPLICANT |
| Issued | 1/5/2023 | APPLICANT |
| CofO in Progress | 11/13/2023 | ENRIQUE MIRELES |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
| CofO Issued | 11/26/2023 | DEROLD HAUFF |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2021 | ROSA SILVA |
| Sewer availability | Cleared | 2/23/2021 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2021 | ROSA SILVA |
| Construction near power lines | Cleared | 7/20/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Manny Walls Remodeling A Partnership; Lic. No.: 1057633-B | 12575 DOLAN AVE DOWNEY, CA 90242 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/13/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/13/2023 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 2/13/2023 | Corrections Issued | ENRIQUE MIRELES |
| Sewer | 2/13/2023 | Corrections Issued | ENRIQUE MIRELES |
| Gas Test | 5/2/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 5/2/2023 | Corrections Issued | ENRIQUE MIRELES |
| Gas Test | 5/8/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 5/8/2023 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 5/15/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/15/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/16/2023 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/16/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 6/16/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 6/16/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/16/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 6/20/2023 | Approved | ENRIQUE MIRELES |
| Shower Pan | 6/20/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/28/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 6/28/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 7/6/2023 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 7/12/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/12/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/28/2023 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/9/2023 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 8/9/2023 | Approved | ENRIQUE MIRELES |
| Special/Order Compliance | 8/30/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 11/3/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 11/3/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 11/3/2023 | Approved | ENRIQUE MIRELES |
| Final | 11/8/2023 | OK to Issue CofO | ENRIQUE MIRELES |