7342 N DARBY AVE 91335
Certificate Information: 7342 N DARBY AVE 91335
- Application / Permit
- 21016-20000-01339
- Plan Check / Job No.
- B21VN00616
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE/ STORAGE TO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). WORK PER WFPP.
- Permit Issued
- Issued on 9/16/2021
- Issuing Office
- Current Status
- CofO Issued on 12/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2021 | ROSENDO MEDINA |
| Corrections Issued | 2/5/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 7/9/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 8/27/2021 | ROSENDO MEDINA |
| Plan Check Approved | 9/3/2021 | ROSENDO MEDINA |
| Building Plans Picked Up | 9/7/2021 | APPLICANT |
| Issued | 9/16/2021 | APPLICANT |
| CofO in Progress | 7/15/2022 | JEFFREY BULL |
| CofO Issued | 12/6/2022 | JOHN JANSON |
| Permit Finaled | 12/6/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/16/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2021 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 5/5/2021 | RIDWAN HARDY |
| Permit | Cleared | 8/11/2021 | GABRIEL ROBLES |
| Trees in Parkway | Cleared | 9/2/2021 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/30/2021 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 10/28/2021 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 11/1/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 11/18/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Underground Mechanical | 11/18/2021 | Partial Approval | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 12/9/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2021 | Partial Approval | VINCENT HANLEY |
| HVAC-Rough | 12/22/2021 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 12/22/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Wood Frame | 12/22/2021 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 3/8/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 3/8/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 3/8/2022 | Approved | VINCENT HANLEY |
| Wood Frame | 3/8/2022 | Partial Approval | VINCENT HANLEY |
| Insulation | 3/23/2022 | Approved | VINCENT HANLEY |
| Wood Frame | 3/23/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 4/11/2022 | No Access for Inspection | JESUS PINEDA |
| Drywall Nailing | 4/14/2022 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 6/10/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 6/10/2022 | Not Ready for Inspection | JEFFREY PARD |
| Final | 6/10/2022 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 6/10/2022 | Corrections Issued | JEFFREY PARD |
| Green Building Rough | 6/10/2022 | Approved | JEFFREY PARD |
| HVAC-Final | 6/10/2022 | Corrections Issued | JEFFREY PARD |
| PLUMBING-Final | 6/10/2022 | Not Ready for Inspection | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 6/10/2022 | SGSOV Not Ready | JEFFREY PARD |
| Service/Power Release | 6/10/2022 | Not Ready for Inspection | JEFFREY PARD |
| Smoke Detectors | 6/10/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 6/17/2022 | Approved | JEFFREY BULL |
| Final | 6/17/2022 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 6/17/2022 | Approved | JEFFREY BULL |
| HVAC-Final | 6/17/2022 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Final | 6/17/2022 | Corrections Issued | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Approved | JEFFREY BULL |
| Gas Test | 6/23/2022 | Approved | MORRIS JACKSON |
| Final | 6/28/2022 | Partial Approval | JEFFREY BULL |
| HVAC-Final | 6/28/2022 | Approved | JEFFREY BULL |
| PLUMBING-Final | 6/28/2022 | Approved | JEFFREY BULL |
| Service/Power Release | 6/28/2022 | Not Ready for Inspection | JEFFREY BULL |