7342 N DARBY AVE 91335

Certificate Information: 7342 N DARBY AVE 91335

Application / Permit
21016-20000-01339
Plan Check / Job No.
B21VN00616
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE/ STORAGE TO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). WORK PER WFPP.
Permit Issued
Issued on 9/16/2021
Issuing Office
Current Status
CofO Issued on 12/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2021 APPLICANT
Assigned to Plan Check Engineer 2/3/2021 ROSENDO MEDINA
Corrections Issued 2/5/2021 ROSENDO MEDINA
Applicant returned to address corrections 7/9/2021 ROSENDO MEDINA
Applicant returned to address corrections 8/27/2021 ROSENDO MEDINA
Plan Check Approved 9/3/2021 ROSENDO MEDINA
Building Plans Picked Up 9/7/2021 APPLICANT
Issued 9/16/2021 APPLICANT
CofO in Progress 7/15/2022 JEFFREY BULL
CofO Issued 12/6/2022 JOHN JANSON
Permit Finaled 12/6/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/16/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/16/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/17/2021 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 5/5/2021 RIDWAN HARDY
Permit Cleared 8/11/2021 GABRIEL ROBLES
Trees in Parkway Cleared 9/2/2021 JOHN KIM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/30/2021 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 10/28/2021 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 11/1/2021 Approved VINCENT HANLEY
Green Building Rough 11/18/2021 Not Ready for Inspection VINCENT HANLEY
Underground Mechanical 11/18/2021 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 12/9/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Partial Approval VINCENT HANLEY
HVAC-Rough 12/22/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 12/22/2021 Not Ready for Inspection VINCENT HANLEY
Wood Frame 12/22/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 3/8/2022 Approved VINCENT HANLEY
HVAC-Rough 3/8/2022 Approved VINCENT HANLEY
PLUMBING-Rough 3/8/2022 Approved VINCENT HANLEY
Wood Frame 3/8/2022 Partial Approval VINCENT HANLEY
Insulation 3/23/2022 Approved VINCENT HANLEY
Wood Frame 3/23/2022 Approved VINCENT HANLEY
Drywall Nailing 4/11/2022 No Access for Inspection JESUS PINEDA
Drywall Nailing 4/14/2022 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 6/10/2022 Approved JEFFREY PARD
ELECTRICAL-Final 6/10/2022 Not Ready for Inspection JEFFREY PARD
Final 6/10/2022 Corrections Issued JEFFREY PARD
Green Building Final 6/10/2022 Corrections Issued JEFFREY PARD
Green Building Rough 6/10/2022 Approved JEFFREY PARD
HVAC-Final 6/10/2022 Corrections Issued JEFFREY PARD
PLUMBING-Final 6/10/2022 Not Ready for Inspection JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 6/10/2022 SGSOV Not Ready JEFFREY PARD
Service/Power Release 6/10/2022 Not Ready for Inspection JEFFREY PARD
Smoke Detectors 6/10/2022 Approved JEFFREY PARD
ELECTRICAL-Final 6/17/2022 Approved JEFFREY BULL
Final 6/17/2022 Corrections Issued JEFFREY BULL
Green Building Final 6/17/2022 Approved JEFFREY BULL
HVAC-Final 6/17/2022 Not Ready for Inspection JEFFREY BULL
PLUMBING-Final 6/17/2022 Corrections Issued JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 6/17/2022 SGSOV Approved JEFFREY BULL
Gas Test 6/23/2022 Approved MORRIS JACKSON
Final 6/28/2022 Partial Approval JEFFREY BULL
HVAC-Final 6/28/2022 Approved JEFFREY BULL
PLUMBING-Final 6/28/2022 Approved JEFFREY BULL
Service/Power Release 6/28/2022 Not Ready for Inspection JEFFREY BULL