8411 W RIDPATH DR 90046

Certificate Information: 8411 W RIDPATH DR 90046

Application / Permit
21016-20000-01334
Plan Check / Job No.
B21VN00614
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 29' 9" X 21' 8" IRR.-SHAPED RECREATION ROOM TO ADU AND ADD 13' 6" X 7' 6" EXTERIOR ENTRY STAIRS/DECK. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 8/2/2021
Issuing Office
Valley
Current Status
CofO Issued on 2/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/19/2021 APPLICANT
Assigned to Plan Check Engineer 1/29/2021 GURUNATH NESARAJAH
Corrections Issued 1/30/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 3/17/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 4/3/2021 GURUNATH NESARAJAH
Plan Check Approved 5/10/2021 GURUNATH NESARAJAH
Building Plans Picked Up 5/11/2021 APPLICANT
Issued 8/2/2021 APPLICANT
CofO in Progress 11/8/2021 RAUL BARAJAS
No Progress 11/9/2021 RAUL BARAJAS
CofO in Progress 11/9/2021 RAUL BARAJAS
CofO in Progress 11/17/2021 RAUL BARAJAS
CofO Issued 2/1/2022 DEROLD HAUFF
Permit Finaled 2/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/16/2021 WALLIE JONG
Sewer availability Cleared 2/16/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/17/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 3/23/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 3/23/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 3/23/2021 WALLIE JONG
Grading Pre-Inspection Cleared 3/26/2021 GURUNATH NESARAJAH
Construction near power lines Cleared 4/30/2021 RIDWAN HARDY
Hold Cleared 8/16/2021 JASON SHEETS

Contact Information

Architect Gritschke,, Andreas Johannes; Lic. No.: C30732 1701 CLINTON STREET APT 301      LOS ANGELES, CA 90026
Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 8/18/2021 Approved RAUL BARAJAS
PLUMBING-Rough 8/18/2021 Approved RAUL BARAJAS
Shower Pan 8/25/2021 Approved RAUL BARAJAS
Footing/Foundation/Slab 8/26/2021 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 9/13/2021 Approved RAUL BARAJAS
Final 9/13/2021 Corrections Issued RAUL BARAJAS
Green Building Final 9/13/2021 Approved RAUL BARAJAS
Green Building Rough 9/13/2021 Approved RAUL BARAJAS
Smoke Detectors 9/13/2021 Approved RAUL BARAJAS
Final 11/8/2021 Conditional Approval RAUL BARAJAS