8250 W 83RD ST 90293
Certificate Information: 8250 W 83RD ST 90293
- Application / Permit
- 21016-20000-01045
- Plan Check / Job No.
- B21VN00532
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO SFD. RELOCATE KITCHEN AND FIREPLACE. ADD NEW PANTRY
- Permit Issued
- Issued on 4/20/2021
- Issuing Office
- Current Status
- Permit Finaled on 11/15/2021
Permit Application Status History
| Submitted | 1/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/4/2021 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 2/19/2021 | APPLICANT |
| Plan Check Approved | 4/10/2021 | MOHAMMAD ESMAILI |
| Issued | 4/20/2021 | APPLICANT |
| Permit Finaled | 11/15/2021 | BOBBY KEY |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Treeium Inc; Lic. No.: 617148-B | 5352 LAUREL CANYON BLVD #200 VALLEY VILLAGE, CA 91607 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/11/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 6/11/2021 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 6/11/2021 | Corrections Issued | BRENDAN LOONEY |
| Underground Mechanical | 6/11/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 6/22/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 6/22/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 6/22/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Underground Mechanical | 6/22/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 7/15/2021 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 7/15/2021 | Approved | BRENDAN LOONEY |
| Rough-Elec/Plmb/HVAC | 7/15/2021 | Partial Approval | BRENDAN LOONEY |
| Insulation | 7/22/2021 | Partial Approval | BRENDAN LOONEY |
| Drywall Nailing | 7/29/2021 | Partial Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 7/29/2021 | Approved | MORRIS JACKSON |
| HVAC-Rough | 9/21/2021 | Corrections Issued | BRENDAN LOONEY |
| Underground Mechanical | 9/30/2021 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 10/4/2021 | Partial Approval | BRENDAN LOONEY |
| Final | 11/15/2021 | Permit Finaled | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 11/15/2021 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 11/15/2021 | Approved | BOBBY KEY |