5832 N DONNA AVE 91356
Certificate Information: 5832 N DONNA AVE 91356
- Application / Permit
- 21016-20000-00973
- Plan Check / Job No.
- B21VN00480
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED REC ROOM / STORAGE ROOM TO ACCESSORY DWELLING UNIT (466 SQ FT) PER LAMC 12.22 A. 33(c) and (e)
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Current Status
- CofO Issued on 3/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 1/31/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 5/24/2021 | JEROME MAGAT PALMA |
| Issued | 5/25/2021 | APPLICANT |
| Building Plans Picked Up | 5/26/2021 | APPLICANT |
| CofO in Progress | 3/1/2022 | SEAN HAUPT |
| Permit Finaled | 3/9/2022 | MICHAEL SMITH |
| CofO Issued | 3/9/2022 | MICHAEL SMITH |
| Permit Finaled | 3/9/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/18/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2021 | GABRIEL ROBLES |
| Miscellaneous | Cleared | 2/18/2021 | LAUREN PADICK |
| Miscellaneous | Cleared | 2/18/2021 | LAUREN PADICK |
| Sewer availability | Cleared | 2/18/2021 | GABRIEL ROBLES |
| Construction within easement | Cleared | 5/25/2021 | JOHN BACON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/24/2021 | No Access for Inspection | STEVEN BACK |
| Deputy Drilled-In Anchors | 9/28/2021 | No Access for Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 9/29/2021 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 9/29/2021 | Not Ready for Inspection | STEVEN BACK |
| Pre-Inspection | 9/29/2021 | Partial Inspection | STEVEN BACK |
| Deputy Drilled-In Anchors | 10/19/2021 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 10/27/2021 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 10/27/2021 | Corrections Issued | SEAN HAUPT |
| Green Building Rough | 10/27/2021 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 10/27/2021 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 11/5/2021 | Approved | SEAN HAUPT |
| Green Building Final | 11/5/2021 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 11/5/2021 | Approved | SEAN HAUPT |
| HVAC-Rough | 11/5/2021 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 11/5/2021 | Approved | SEAN HAUPT |
| Shower Pan | 11/5/2021 | Approved | SEAN HAUPT |
| Insulation | 11/10/2021 | Approved | SEAN HAUPT |
| Drywall Nailing | 11/17/2021 | Approved | SEAN HAUPT |
| Pre-Inspection | 11/17/2021 | Approved | SEAN HAUPT |
| Underground Mechanical | 12/28/2021 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 2/9/2022 | Approved | SEAN HAUPT |
| Final | 2/9/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 2/9/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Final | 2/9/2022 | Approved | SEAN HAUPT |
| MERV13>=Final | 2/9/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 2/9/2022 | Approved | SEAN HAUPT |
| Smoke Detectors | 2/9/2022 | Approved | SEAN HAUPT |
| Final | 3/1/2022 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 3/1/2022 | Approved | SEAN HAUPT |