10544 W BUTTERFIELD ROAD 90064

Certificate Information: 10544 W BUTTERFIELD ROAD 90064

Application / Permit
21016-20000-00801
Plan Check / Job No.
B21VN00358
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 18' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER DESIGN.
Permit Issued
Issued on 5/7/2021
Issuing Office
Current Status
CofO Issued on 12/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2021 APPLICANT
Assigned to Plan Check Engineer 1/26/2021 JENNIFER LEE
Corrections Issued 1/27/2021 JENNIFER LEE
Plan Check Approved 5/6/2021 JENNIFER LEE
Issued 5/7/2021 APPLICANT
Building Plans Picked Up 5/10/2021 APPLICANT
CofO in Progress 12/17/2021 OGANES TARAKHCHYAN
Permit Finaled 12/23/2021 KENNETH NAGLE
CofO Issued 12/23/2021 KENNETH NAGLE
Permit Finaled 12/23/2021 KENNETH NAGLE

Permit Application Clearance Information

Specific Plan Cleared 1/29/2021 LAUREN PADICK
Grading Pre-Inspection Cleared 2/4/2021 BRIAN MILLER
Address approval Cleared 2/5/2021 DINAH GARIN
Sewer availability Cleared 2/5/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/8/2021 DINAH GARIN
Specific Plan Cleared 3/1/2021 VALERIA CEJA
Construction near power lines Cleared 4/27/2021 RIDWAN HARDY
Construction within easement Cleared 4/27/2021 RIDWAN HARDY

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Karma Remodel & Development Inc; Lic. No.: 875130-B 21610 VENTURA BLVD      WOODLAND HILLS, CA 91364

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/28/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 7/2/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 7/6/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 7/8/2021 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 7/8/2021 Partial Approval KEVIN SARGSYAN
Sewer 7/8/2021 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 7/19/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 7/20/2021 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 7/22/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 7/23/2021 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 8/6/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 8/10/2021 Corrections Issued EVAN COOPER
Special/Order Compliance 8/11/2021 Approved EVAN COOPER
Footing/Foundation/Slab 8/17/2021 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 8/19/2021 Approved KEVIN SARGSYAN
Rough-Elec/Plmb/HVAC 9/14/2021 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 9/20/2021 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/20/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 9/20/2021 Not Ready for Inspection KEVIN SARGSYAN
Rough-Elec/Plmb/HVAC 9/20/2021 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 9/27/2021 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Approved JAVIER RAMOS JR
Green Building Rough 9/27/2021 Not Ready for Inspection JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 9/27/2021 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 10/1/2021 Approved KENNETH NAGLE
Green Building Rough 10/1/2021 Approved KENNETH NAGLE
Insulation 10/1/2021 Approved KENNETH NAGLE
Interior/Exterior Lathing 10/1/2021 Approved KENNETH NAGLE
Shower Pan 10/1/2021 Approved KENNETH NAGLE
Drywall Nailing 10/5/2021 Approved KRISTEN CAUSEY
Insulation 10/5/2021 Partial Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 10/5/2021 Partial Inspection KRISTEN CAUSEY
Shower Pan 10/5/2021 Partial Inspection KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 11/24/2021 SGSOV Not Ready KEVIN SARGSYAN
Final 12/8/2021 Corrections Issued KEVIN SARGSYAN
Green Building Final 12/8/2021 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/8/2021 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 12/8/2021 Approved KEVIN SARGSYAN
Final 12/13/2021 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 12/16/2021 Approved OGANES TARAKHCHYAN
Final 12/16/2021 OK to Issue CofO OGANES TARAKHCHYAN
HVAC-Final 12/16/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Final 12/16/2021 Approved OGANES TARAKHCHYAN