8517 W APPIAN WAY 90046
Certificate Information: 8517 W APPIAN WAY 90046
- Application / Permit
- 21016-20000-00779
- Plan Check / Job No.
- B21VN00339
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) SFD TO REMOVE FIREPLACE, CONVERT BATHROOM TO LAUNDRY, CONVERT CLOSET TO MASTER BATHROOM AND CONVERT LAUNDRY ROOM TO CLOSET. NO STRUCTURAL CHANGES TO BE MADE.
- Permit Issued
- Issued on 2/23/2021
- Issuing Office
- Current Status
- Permit Finaled on 1/26/2026
Permit Application Status History
| Submitted | 1/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 1/26/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 2/22/2021 | GURUNATH NESARAJAH |
| Issued | 2/23/2021 | APPLICANT |
| Building Plans Picked Up | 2/26/2021 | APPLICANT |
| Permit Finaled | 1/23/2026 | SCOTT FINNILA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Luxe Development Inc; Lic. No.: 993473-B | 329 N WETHERLY DRIVE #205 BEVERLY HILLS, CA 90211 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/13/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/13/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 4/15/2021 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 4/21/2021 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 4/21/2021 | Approved | RAUL BARAJAS |
| HVAC-Rough | 4/21/2021 | Approved | RAUL BARAJAS |
| Insulation | 4/21/2021 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 4/21/2021 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 4/21/2021 | Approved | RAUL BARAJAS |
| Shower Pan | 4/21/2021 | Approved | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 4/28/2021 | Conditional Approval | THOMAS LOGRASSO |
| Gas Test | 5/3/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/3/2021 | Approved | THOMAS LOGRASSO |
| Special/Order Compliance | 5/28/2021 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 9/1/2021 | Corrections Issued | BRAD BESCOS |
| Final | 9/1/2021 | Not Ready for Inspection | BRAD BESCOS |
| HVAC-Final | 9/1/2021 | Corrections Issued | BRAD BESCOS |
| PLUMBING-Final | 9/1/2021 | Corrections Issued | BRAD BESCOS |
| SGSOV-Seismic Gas S/O Valve | 9/1/2021 | SGSOV Not Ready | BRAD BESCOS |
| Smoke Detectors | 9/1/2021 | Approved | BRAD BESCOS |
| ELECTRICAL-Final | 9/16/2021 | Partial Approval | RAUL BARAJAS |
| Final | 9/16/2021 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Final | 9/16/2021 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 9/16/2021 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 9/16/2021 | SGSOV Not Ready | RAUL BARAJAS |
| Final | 11/20/2025 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 11/20/2025 | SGSOV Approved | ROY SPAULDING |
| Final | 1/23/2026 | Permit Finaled | SCOTT FINNILA |