7427-7429 N NESTLE AVE 91335
Certificate Information: 7427-7429 N NESTLE AVE 91335
- Application / Permit
- 21016-20000-00527
- Plan Check / Job No.
- B21VN00252
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT GARAGE TO ACCESSORY DWELLING UNIT ( 18'-3"X20'-6") PER CA GOVT. CODE 65852.2(e)(1)(A). ALL WORK PER WFPP
- Permit Issued
- Issued on 3/12/2021
- Issuing Office
- Current Status
- CofO Corrected on 10/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 1/21/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 2/17/2021 | OMAR GARNICA |
| Issued | 3/12/2021 | APPLICANT |
| CofO in Progress | 8/16/2021 | VINCENT HANLEY |
| CofO Issued-Status Void | 8/18/2021 | MICHAEL SMITH |
| Permit Finaled-Status Void | 8/18/2021 | MICHAEL SMITH |
| Re-Activate Permit | 10/12/2021 | MICHAEL SMITH |
| CofO Corrected | 10/12/2021 | MICHAEL SMITH |
| Permit Finaled | 10/12/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/5/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/5/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2021 | ADRIAN CASTRO |
Contact Information
| No Data Available. |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/23/2021 | Approved | VINCENT HANLEY |
| Final | 3/23/2021 | Corrections Issued | VINCENT HANLEY |
| Sewer | 3/23/2021 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/26/2021 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 3/26/2021 | Partial Approval | VINCENT HANLEY |
| Sewer | 3/26/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/20/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Gas Test | 4/20/2021 | Partial Approval | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 4/20/2021 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/28/2021 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 4/28/2021 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 4/28/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 4/28/2021 | Corrections Issued | HENRY KIM |
| Gas Test | 5/6/2021 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 5/6/2021 | Partial Approval | VINCENT HANLEY |
| Wood Frame | 5/6/2021 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/12/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/12/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/12/2021 | Partial Approval | VINCENT HANLEY |
| Insulation | 5/13/2021 | Approved | LILIANA PORTILLO |
| Special/Order Compliance | 5/13/2021 | Partial Inspection | STEPHANIE SWANSON |
| Drywall Nailing | 5/20/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/20/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Shower Pan | 5/20/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/26/2021 | Approved | LILIANA PORTILLO |
| Shower Pan | 5/26/2021 | Approved | LILIANA PORTILLO |
| Final | 7/26/2021 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 7/26/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/26/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 7/26/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/29/2021 | Approved | DAVID STEPANYAN |
| Final | 7/29/2021 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Final | 7/29/2021 | Approved | DAVID STEPANYAN |
| Gas Test | 8/2/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 8/16/2021 | Approved | VINCENT HANLEY |
| Final | 8/16/2021 | OK to Issue CofO | VINCENT HANLEY |
| Gas Test | 8/16/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 8/16/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 8/16/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 8/16/2021 | Approved | VINCENT HANLEY |