3331 S BENTLEY AVE 90034
Certificate Information: 3331 S BENTLEY AVE 90034
- Application / Permit
- 21016-20000-00480
- Plan Check / Job No.
- B21VN00214
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) SFD ST (E) BATHROOM AND KITCHEN. WORK PER ENGINEER.
- Permit Issued
- Issued on 3/10/2021
- Issuing Office
- Current Status
- Permit Finaled on 9/3/2021
Permit Application Status History
| Submitted | 1/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 1/21/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 2/11/2021 | ROSENDO MEDINA |
| No Progress | 3/3/2021 | JON BLAINE |
| Issued | 3/10/2021 | APPLICANT |
| Permit Finaled | 9/2/2021 | OGANES TARAKHCHYAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/11/2021 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Pearl Remodeling; Lic. No.: 955824-B | 6803 YARMOUTH AVENUE RESEDA, CA 91335 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/15/2021 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 4/15/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 4/30/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 4/30/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 4/30/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/30/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/3/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/5/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 5/11/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/21/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/21/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 7/21/2021 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Rough | 7/21/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/21/2021 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 7/23/2021 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 7/27/2021 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/27/2021 | Approved | JESUS RODRIGUEZ |
| Final | 9/2/2021 | Permit Finaled | OGANES TARAKHCHYAN |
| MERV13>=Final | 9/2/2021 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/2/2021 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/2/2021 | Approved | OGANES TARAKHCHYAN |