6810 N DELCO AVE 91306
Certificate Information: 6810 N DELCO AVE 91306
- Application / Permit
- 21016-20000-00319
- Plan Check / Job No.
- B21VN00137
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2. WORK PER WFPP.
- Permit Issued
- Issued on 4/8/2021
- Issuing Office
- Current Status
- Issued on 4/8/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2021 | ROSENDO MEDINA |
| Corrections Issued | 1/22/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 3/5/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 4/3/2021 | ROSENDO MEDINA |
| Plan Check Approved | 4/8/2021 | ROSENDO MEDINA |
| Issued | 4/8/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/3/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/3/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/4/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 1/10/2022 | Partial Approval | STEVEN BACK |
| Sewer | 1/10/2022 | Approved | STEVEN BACK |
| Underground Mechanical | 1/10/2022 | Corrections Issued | STEVEN BACK |
| Underground Mechanical | 1/13/2022 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 2/28/2022 | No Access for Inspection | STEVEN BACK |
| Footing/Foundation/Slab | 3/4/2022 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/6/2025 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Rough | 11/6/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Green Building Rough | 11/6/2025 | Not Ready for Inspection | JUAN ALVARADO |
| PLUMBING-Rough | 11/6/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Pre-Inspection | 11/6/2025 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Rough | 11/12/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 11/12/2025 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 11/12/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 11/20/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Interior/Exterior Lathing | 11/20/2025 | Corrections Issued | JUAN ALVARADO |
| BUILDING-Rough-Frame | 11/26/2025 | Corrections Issued | JUAN ALVARADO |
| Green Building Rough | 11/26/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Interior/Exterior Lathing | 11/26/2025 | Partial Approval | JUAN ALVARADO |
| BUILDING-Rough-Frame | 12/15/2025 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 12/15/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 1/14/2026 | Approved | ALEXANDER HANDY |
| Insulation | 1/14/2026 | Approved | ALEXANDER HANDY |
| Shower Pan | 1/14/2026 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 1/16/2026 | Corrections Issued | DAVID FASTIGGI |
| Interior/Exterior Lathing | 1/16/2026 | Approved | DAVID FASTIGGI |
| Drywall Nailing | 1/21/2026 | Approved | DAVID FASTIGGI |
| Final | 3/11/2026 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 3/11/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 3/11/2026 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 3/16/2026 | Approved | ALEXANDER HANDY |
| Final | 3/16/2026 | Partial Inspection | ALEXANDER HANDY |
| Green Building Final | 3/16/2026 | Approved | ALEXANDER HANDY |
| HVAC-Final | 3/16/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 3/16/2026 | Approved | ALEXANDER HANDY |
| Service/Power Release | 3/16/2026 | Approved | ALEXANDER HANDY |