6922 W SHADYGROVE ST 91042
Certificate Information: 6922 W SHADYGROVE ST 91042
- Application / Permit
- 21016-20000-00293
- Plan Check / Job No.
- B21VN00121
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE & STORAGE BUILDING TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND ADD PATIO COVER (7'-8" X 4'-6")
- Permit Issued
- Issued on 4/26/2021
- Issuing Office
- Current Status
- CofO Issued on 10/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/12/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/12/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 1/13/2021 | APPLICANT |
| Plan Check Approved | 4/23/2021 | NILOOFAR MEHRAIN |
| Issued | 4/26/2021 | APPLICANT |
| CofO in Progress | 9/27/2021 | MATTHEW NELSON |
| Permit Finaled | 10/18/2021 | MICHAEL SMITH |
| CofO Issued | 10/18/2021 | MICHAEL SMITH |
| Permit Finaled | 10/18/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/14/2021 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 1/14/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 1/14/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2021 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 1/19/2021 | BRIAN MILLER |
| Hydrant and Access approval | Cleared | 2/22/2021 | MATTHEW CRAIG |
| Specific Plan | Cleared | 4/12/2021 | PEGGY MALONE-BROWN |
| ZI | Cleared | 4/12/2021 | PEGGY MALONE-BROWN |
Contact Information
| Architect | Menachekanian,, Asik A; Lic. No.: C28213 | 9773 VIA NOLA BURBANK, CA 91504 |
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/1/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/16/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/16/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 7/16/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 7/16/2021 | Approved | MATTHEW NELSON |
| Insulation | 7/16/2021 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 7/16/2021 | Approved | MATTHEW NELSON |
| Insulation | 7/23/2021 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 7/23/2021 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 7/28/2021 | Approved | JAVIER RAMOS JR |
| Green Building Final | 8/27/2021 | Approved | MATTHEW NELSON |
| HVAC-Final | 8/27/2021 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 8/27/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 9/7/2021 | Approved | MATTHEW NELSON |
| Final | 9/7/2021 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/7/2021 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 9/7/2021 | Approved | MATTHEW NELSON |
| Final | 9/8/2021 | Partial Approval | MATTHEW NELSON |
| Final | 9/27/2021 | OK to Issue CofO | MATTHEW NELSON |