20608 W OVERLOOK CT 91326

Certificate Information: 20608 W OVERLOOK CT 91326

Application / Permit
21016-20000-00292
Plan Check / Job No.
B21VN00120
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT GARAGE INTO SALES OFFICE & STRIPE FOR (N) PARKING LOT FOR MODEL HOME & ADD BATHROOM WITHIN GARAGE
Permit Issued
Issued on 6/22/2021
Issuing Office
Current Status
Permit Finaled on 2/17/2023

Permit Application Status History

Submitted 1/6/2021 APPLICANT
Disabled Access Plans Picked Up 1/27/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 NILOOFAR MEHRAIN
Corrections Issued 2/9/2021 NILOOFAR MEHRAIN
Quality Review Completed 2/16/2021 CHON CHIO KUO
Building Plans Picked Up 2/19/2021 APPLICANT
Applicant returned to address corrections 4/19/2021 NILOOFAR MEHRAIN
Plan Check Approved 5/12/2021 NILOOFAR MEHRAIN
Issued 6/22/2021 APPLICANT
Permit Finaled 2/15/2023 JEFFREY FULTON

Permit Application Clearance Information

DAS Clearance Cleared 3/18/2021 NORLITO MEDRANO
Eng Process Fee Ord 176,300 Cleared 3/22/2021 LEE GUILBEAUX
Sewer availability Cleared 3/22/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/22/2021 LEE GUILBEAUX
"T" removal Cleared 6/8/2021 DANG NGUYEN
Specific Plan Cleared 6/8/2021 DANG NGUYEN
Tract Map conditions Cleared 6/8/2021 DANG NGUYEN
Tract Map conditions Cleared 6/8/2021 DANG NGUYEN
ZA Case Cleared 6/8/2021 DANG NGUYEN
ZA Case Cleared 6/8/2021 DANG NGUYEN
ZI Cleared 6/8/2021 DANG NGUYEN

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034
Engineer Wong,, Ramon Roman; Lic. No.: S2345 1800 E. 16TH STREET      SANTA ANA, CA 92701

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 11/9/2021 Approved JEFFREY FULTON
Wood Frame 11/9/2021 Partial Inspection JEFFREY FULTON
Final 3/10/2022 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 3/10/2022 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 3/10/2022 Not Ready for Inspection JEFFREY FULTON
Wood Frame 3/10/2022 Not Ready for Inspection JEFFREY FULTON
Final 3/16/2022 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 3/16/2022 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 3/16/2022 Not Ready for Inspection JEFFREY FULTON
Wood Frame 3/16/2022 Not Ready for Inspection JEFFREY FULTON
Final 3/23/2022 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 3/23/2022 SGSOV Approved JEFFREY FULTON
Smoke Detectors 3/23/2022 Approved JEFFREY FULTON
Wood Frame 3/23/2022 Approved JEFFREY FULTON
Final 3/25/2022 Partial Inspection JEFFREY FULTON
Special/Order Compliance 8/24/2022 Partial Inspection JEFFREY FULTON
Final 10/27/2022 OK for TCO JEFFREY DURAN
Final 2/15/2023 Permit Finaled JEFFREY FULTON