19622 W SCHOOLCRAFT ST 91335

Certificate Information: 19622 W SCHOOLCRAFT ST 91335

Application / Permit
21016-20000-00244
Plan Check / Job No.
B21VN00107
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER ORD #186,481. ALL WORK PER WFPP.
Permit Issued
Issued on 4/21/2021
Issuing Office
Current Status
CofO Issued on 12/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2021 APPLICANT
Assigned to Plan Check Engineer 1/15/2021 HAYATO TSUCHIYA
Corrections Issued 1/18/2021 HAYATO TSUCHIYA
Plan Check Approved 4/6/2021 PETER MOSESIAN
Issued 4/21/2021 APPLICANT
CofO in Progress 12/19/2021 VINCENT HANLEY
CofO Issued 12/30/2021 MICHAEL SMITH
Permit Finaled 12/30/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/21/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/21/2021 ADRIAN CASTRO
Sewer availability Cleared 1/21/2021 ADRIAN CASTRO
Construction near power lines Cleared 3/31/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/16/2021 Conditional Approval JUSTIN HAWLEY
Footing/Foundation/Slab 6/17/2021 Approved VINCENT HANLEY
PLUMBING-Rough 6/17/2021 Partial Approval VINCENT HANLEY
Underground Mechanical 6/17/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/2/2021 Approved VINCENT HANLEY
Wood Frame 7/2/2021 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 7/15/2021 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 9/10/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 9/10/2021 Approved VINCENT HANLEY
Green Building Rough 9/10/2021 Approved VINCENT HANLEY
HVAC-Rough 9/10/2021 Approved VINCENT HANLEY
PLUMBING-Rough 9/10/2021 Approved VINCENT HANLEY
Sewer 9/10/2021 Approved VINCENT HANLEY
Insulation 9/16/2021 Approved VINCENT HANLEY
Shower Pan 9/16/2021 Approved VINCENT HANLEY
Drywall Nailing 9/24/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Approved VINCENT HANLEY
Footing/Foundation/Slab 10/21/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 10/21/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 12/17/2021 Approved VINCENT HANLEY
Final 12/17/2021 OK to Issue CofO VINCENT HANLEY
Green Building Final 12/17/2021 Approved VINCENT HANLEY
HVAC-Final 12/17/2021 Approved VINCENT HANLEY
PLUMBING-Final 12/17/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/17/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 12/17/2021 Approved VINCENT HANLEY