19198-19200 W ERWIN ST 91335
Certificate Information: 19198-19200 W ERWIN ST 91335
- Application / Permit
- 21016-20000-00088
- Plan Check / Job No.
- B21VN00020
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 19' 6" X 17' 10" ATTACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 4/21/2021
- Issuing Office
- Current Status
- CofO Issued on 1/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 1/17/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/14/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 3/16/2021 | APPLICANT |
| Issued | 4/21/2021 | APPLICANT |
| CofO in Progress | 1/5/2022 | SEAN HAUPT |
| CofO in Progress | 1/6/2022 | SEAN HAUPT |
| CofO Issued | 1/29/2022 | MICHAEL SMITH |
| Permit Finaled | 1/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/2/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | JOHN TRIANTAFYLLOS |
| ZI | Cleared | 2/23/2021 | DANG NGUYEN |
Contact Information
| Contractor | Lee'S General Construction Corp; Lic. No.: 1056618-B | 2215 S ELECTRIC AVE ALHAMBRA, CA 91803 |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/11/2021 | Corrections Issued | STEVEN BACK |
| Gas Test | 5/11/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 5/11/2021 | Corrections Issued | STEVEN BACK |
| Pre-Inspection | 5/11/2021 | Partial Inspection | STEVEN BACK |
| Sewer | 5/11/2021 | Approved | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 5/20/2021 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 5/20/2021 | Approved | STEVEN BACK |
| Gas Test | 5/20/2021 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 5/20/2021 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 6/17/2021 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 6/17/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 6/17/2021 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 6/25/2021 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 6/25/2021 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 6/25/2021 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 6/25/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 6/25/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 9/10/2021 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 9/10/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2021 | Partial Approval | STEVEN BACK |
| Gas Test | 9/10/2021 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 9/10/2021 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 9/28/2021 | Conditional Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2021 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 9/28/2021 | Partial Approval | STEVEN BACK |
| Deputy Wood Construction | 10/1/2021 | Conditional Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 10/7/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 10/7/2021 | Partial Approval | STEVEN BACK |
| Insulation | 10/7/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 10/20/2021 | Approved | SEAN HAUPT |
| Final | 12/17/2021 | Corrections Issued | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/17/2021 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 12/17/2021 | Approved | SEAN HAUPT |
| Final | 1/4/2022 | OK to Issue CofO | SEAN HAUPT |
| Service/Power Release | 1/4/2022 | Approved | SEAN HAUPT |