1026 W 22ND ST 90007

Certificate Information: 1026 W 22ND ST 90007

Application / Permit
21016-10004-03483
Plan Check / Job No.
B24LA23660
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(15) Telecommunication Transmitter - wireless
Work Description
SUPPLEMENTAL TO 21016-10000-03483. ALTERATION TO ROOF ANTENNA SYSTEM, UPDATE DIMENSIONS OF ROOF AND ADD STRUT DETAILS.
Permit Issued
Issued on 2/11/2025
Issuing Office
Current Status
Issued on 2/11/2025

Permit Application Status History

Submitted 9/19/2024 APPLICANT
Assigned to Plan Check Engineer 9/24/2024 FERNANDO FLORES
Corrections Issued 9/26/2024 FERNANDO FLORES
Building Plans Picked Up 9/30/2024 APPLICANT
Applicant returned to address corrections 2/4/2025 CRISTINA SALAZAR
Plan Check Approved 2/11/2025 CRISTINA SALAZAR
Issued 2/11/2025 APPLICANT

Permit Application Clearance Information

"Q" conditions Cleared 12/16/2024 LESLIE PEREZ
Miscellaneous Cleared 12/16/2024 LESLIE PEREZ
Miscellaneous Cleared 12/16/2024 LESLIE PEREZ
Plan Approval Cleared 12/16/2024 LESLIE PEREZ
ZA Case Cleared 12/16/2024 LESLIE PEREZ
HPOZ Cleared 1/24/2025 MICAELA TORRES-GIL

Contact Information

Contractor 3 S Network Inc; Lic. No.: 975955-B 1541 PARKWAY LOOP SUITE E      TUSTIN, CA 92780
Engineer Yang,, Yunxiao; Lic. No.: C87746 63 APPLESEED LN      GAITHERSBURG, MD 20878

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/26/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Pre-Inspection 2/28/2025 Not Ready for Inspection ALFREDO LOPEZ
Pre-Inspection 3/17/2025 Partial Approval ALFREDO LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/24/2025 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 3/24/2025 Partial Approval ALFREDO LOPEZ
Pre-Inspection 3/27/2025 Partial Inspection ALFREDO LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Approved ALFREDO LOPEZ
Wood Frame 4/3/2025 Approved ALFREDO LOPEZ
Final 4/24/2025 Partial Inspection ALFREDO LOPEZ
Smoke Detectors 4/24/2025 Not Ready for Inspection ALFREDO LOPEZ