600 W 7TH ST 100 90017
Certificate Information: 600 W 7TH ST 100 90017
- Application / Permit
- 21016-10003-59345
- Plan Check / Job No.
- B23LA21859
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- SUPPLEMENTAL TO PERMIT # 21016-10000-59345 FOR MINOR REVISIONS AND RATING CLARIFICATIONS: PROVIDE NEW FULL HEIGHT PARTITIONS, NEW ACCESS PANEL, AND NEW HARD-LID CEILING WHERE INDICATED ON PLANS.
- Permit Issued
- Issued on 4/2/2024
- Issuing Office
- Current Status
- Permit Finaled on 2/24/2025
Permit Application Status History
| Submitted | 11/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | MICHAEL LOPEZ |
| Disabled Access Plans Picked Up | 11/30/2023 | APPLICANT |
| Corrections Issued | 12/5/2023 | MICHAEL LOPEZ |
| Quality Review Completed | 12/8/2023 | KEN GILL |
| Building Plans Picked Up | 12/11/2023 | APPLICANT |
| Green Plans Picked Up | 12/21/2023 | APPLICANT |
| Plan Check Approved | 2/9/2024 | MICHAEL LOPEZ |
| Issued | 4/2/2024 | APPLICANT |
| Permit Finaled | 2/3/2025 | PAUL BAZERKANIAN |
Permit Application Clearance Information
| Green Code | Cleared | 1/17/2024 | AARON COSTA |
| Fire Marshal Fire Life Safety | Cleared | 1/22/2024 | MENOA AGHAJANI |
| DAS Clearance | Cleared | 1/25/2024 | SHINE LIN |
Contact Information
| Architect | Chan,, John Tuen-Jon; Lic. No.: C16828 | 65 N FIRST AVENUE SUITE 201 ARCADIA, CA 91006 |
| Contractor | Clune Construction Company L P; Lic. No.: 732107-B | 725 SOUTH FIGUEROA STREET STE 300 LOS ANGELES, CA 90017 |
| Engineer | Li,, Lai; Lic. No.: C89944 | 550 N SAINT CLAIR ST UNIT 1603 CHICAGO, IL 60611 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 4/18/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 4/18/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 4/22/2024 | Partial Approval | LUIS CCAMACHO |
| Insulation | 4/22/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 6/11/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 6/12/2024 | Partial Approval | LUIS CCAMACHO |
| Insulation | 6/12/2024 | Partial Approval | LUIS CCAMACHO |
| Insulation | 9/26/2024 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 9/26/2024 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 9/30/2024 | Partial Approval | PAUL BAZERKANIAN |
| Final | 2/3/2025 | Permit Finaled | PAUL BAZERKANIAN |
| Green Building Final | 2/3/2025 | Approved | PAUL BAZERKANIAN |
| Smoke Detectors | 2/3/2025 | Approved | PAUL BAZERKANIAN |