3124-3126 N BARBARA CT 90068

Certificate Information: 3124-3126 N BARBARA CT 90068

Application / Permit
21016-10003-14512
Plan Check / Job No.
B23LA14145
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL PERMIT TO 21016-10000-14512: CONVERT LOWER LEVEL STORAGE AREA TO A.D.U. PER STATE LAW. ( 819 S.F. )
Permit Issued
Issued on 10/11/2023
Issuing Office
Valley
Current Status
Permit Finaled on 1/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2023 APPLICANT
Assigned to Plan Check Engineer 8/9/2023 LAWRENCE QUIRANTE
Corrections Issued 8/14/2023 LAWRENCE QUIRANTE
Building Plans Picked Up 8/17/2023 APPLICANT
Plan Check Approved 10/6/2023 ADAM HEGAZI
Issued 10/11/2023 APPLICANT
Permit Finaled 1/29/2024 HAGOP BADOSSIAN

Permit Application Clearance Information

Address approval Cleared 8/24/2023 JOSEPH RHYU
Eng Process Fee Ord 176,300 Cleared 8/24/2023 JOSEPH RHYU
Sewer availability Cleared 8/24/2023 JOSEPH RHYU
Specific Plan Cleared 10/4/2023 JUDE HERNANDEZ

Contact Information

Architect Gemigniani,, Richard Louis; Lic. No.: C18783 4069 WOODCLIFF RD      SHERMAN OAKS, CA 91403
Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/12/2023 Corrections Issued PATRICK LIEBREGT
BUILDING-Rough-Frame 1/24/2024 Not Ready for Inspection HAGOP BADOSSIAN
Final 1/24/2024 Not Ready for Inspection HAGOP BADOSSIAN
MERV13>=Final 1/24/2024 No Access for Inspection HAGOP BADOSSIAN
MERV13>=Rough 1/24/2024 Approved HAGOP BADOSSIAN
Smoke Detectors 1/24/2024 Approved HAGOP BADOSSIAN
BUILDING-Rough-Frame 1/29/2024 Approved HAGOP BADOSSIAN
ELECTRICAL-Final 1/29/2024 Approved HAGOP BADOSSIAN
Final 1/29/2024 Permit Finaled HAGOP BADOSSIAN
HVAC-Final 1/29/2024 Approved HAGOP BADOSSIAN
MERV13>=Final 1/29/2024 Approved HAGOP BADOSSIAN
PLUMBING-Final 1/29/2024 Approved HAGOP BADOSSIAN