Deputy Drilled-In Anchors
|
8/29/2024
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Deputy Reinf. Concrete
|
8/29/2024
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Deputy Shotcrete
|
9/12/2024
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/12/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Green Building Rough
|
9/12/2024
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
METHANE-Rough
|
9/12/2024
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Reinforced Concrete Frame
|
9/12/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Green Building Rough
|
9/17/2024
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
METHANE-Rough
|
9/17/2024
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Reinforced Concrete Frame
|
9/17/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
9/25/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Green Building Rough
|
9/27/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
METHANE-Rough
|
9/27/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Reinforced Concrete Frame
|
9/27/2024
|
Partial Inspection
|
RAMAZANALI ALMASI
|
|
Footing/Foundation/Slab
|
10/1/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
10/3/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
10/9/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Green Building Rough
|
10/9/2024
|
Approved
|
RONALD JIMENEZ
|
|
METHANE-Rough
|
10/9/2024
|
Approved
|
RONALD JIMENEZ
|
|
Reinforced Concrete Frame
|
10/9/2024
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
10/11/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Reinforced Concrete Frame
|
10/11/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
10/15/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Piling/Pier/Caisson
|
10/15/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
10/16/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Footing/Foundation/Slab
|
10/17/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Reinforced Concrete Frame
|
10/17/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
10/24/2024
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Reinforced Concrete Frame
|
10/24/2024
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/28/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Deputy Shotcrete
|
10/29/2024
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
10/29/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Special/Order Compliance
|
10/29/2024
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
11/4/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Reinforced Concrete Frame
|
11/4/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/6/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
11/6/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Reinforced Concrete Frame
|
11/7/2024
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
11/8/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Footing/Foundation/Slab
|
11/12/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
11/18/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
11/21/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
11/26/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
12/6/2024
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Reinforced Concrete Frame
|
12/6/2024
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
12/9/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Structural Steel Frame
|
12/9/2024
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
12/12/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Reinforced Concrete Frame
|
12/26/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
1/6/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
1/9/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/9/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
1/10/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/10/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/17/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Reinforced Concrete Frame
|
1/17/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
1/21/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
1/27/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/27/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Special/Order Compliance
|
1/27/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Structural Steel Frame
|
1/27/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
1/30/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/4/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/20/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
2/21/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
2/26/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/26/2025
|
Approved
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
3/4/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
3/5/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/5/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
3/11/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/11/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Excavation/Setback/Form/Re-Bar
|
3/13/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/19/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
3/25/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Excavation/Setback/Form/Re-Bar
|
3/25/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/25/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/27/2025
|
Approved
|
DARRYL ARNOLD
|
|
Footing/Foundation/Slab
|
3/27/2025
|
Approved
|
DARRYL ARNOLD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/8/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/10/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
4/10/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Structural Steel Frame
|
4/10/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Excavation/Setback/Form/Re-Bar
|
4/14/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
4/14/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/16/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Wood Frame
|
4/16/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Masonry Wall/Backfill
|
4/18/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
4/21/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
4/22/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Excavation/Setback/Form/Re-Bar
|
4/23/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
4/23/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Reinforced Masonry Frame
|
4/23/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Reinforced Concrete Frame
|
4/24/2025
|
Approved
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
4/25/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/25/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
4/25/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
4/30/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/30/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
4/30/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
4/30/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
5/1/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
5/5/2025
|
Conditional Approval
|
DARRYL ARNOLD
|
|
Footing/Foundation/Slab
|
5/5/2025
|
Conditional Approval
|
DARRYL ARNOLD
|
|
Insulation
|
5/5/2025
|
Conditional Approval
|
DARRYL ARNOLD
|
|
Light Gage Steel Frame
|
5/5/2025
|
Conditional Approval
|
DARRYL ARNOLD
|
|
Drywall Nailing
|
5/6/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
5/6/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
5/8/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
5/8/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
5/12/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/14/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
5/14/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
5/14/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
5/16/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
5/19/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/19/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
5/19/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Structural Steel Frame
|
5/19/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
5/20/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
5/20/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
5/27/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
5/27/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
5/27/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
5/27/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
5/27/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
5/29/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
5/29/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
6/2/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
6/2/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
6/2/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
6/2/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
6/3/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
6/4/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
6/4/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Interior/Exterior Lathing
|
6/4/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
6/4/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
6/9/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
6/9/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
6/9/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Interior/Exterior Lathing
|
6/10/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
6/10/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
6/12/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
6/12/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
6/17/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
6/17/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
6/17/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
6/17/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
6/20/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
6/24/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/24/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
6/24/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Interior/Exterior Lathing
|
6/24/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
6/24/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
6/25/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
6/26/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
6/26/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
6/26/2025
|
Partial Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
6/30/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
7/3/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
7/3/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
7/7/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
7/7/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Insulation
|
7/8/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Interior/Exterior Lathing
|
7/8/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
7/8/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
7/9/2025
|
Approved
|
RONALD JIMENEZ
|
|
Interior/Exterior Lathing
|
7/14/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
7/17/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
7/17/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
7/22/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
7/22/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
7/22/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
7/29/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
7/29/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
7/31/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
7/31/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Special/Order Compliance
|
7/31/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
T-Bar Ceiling
|
7/31/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
7/31/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
8/5/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Structural Steel Frame
|
8/5/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Wood Frame
|
8/5/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
8/6/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
8/6/2025
|
Approved
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
8/6/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
8/7/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Insulation
|
8/7/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
8/7/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
8/8/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
8/8/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
8/12/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
8/14/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Insulation
|
8/14/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
8/14/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
8/18/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
8/18/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
8/20/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
8/20/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
8/20/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
8/21/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
T-Bar Ceiling
|
8/25/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
8/25/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
8/26/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Special/Order Compliance
|
8/26/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Wood Frame
|
8/26/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
8/28/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
8/28/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
8/28/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
8/29/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/29/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
8/29/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
9/3/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
9/3/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Special/Order Compliance
|
9/3/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
9/4/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
9/4/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Special/Order Compliance
|
9/8/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
9/9/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
9/12/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
9/12/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
9/12/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
9/23/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/23/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Insulation
|
9/23/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Interior/Exterior Lathing
|
9/23/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
9/23/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
9/23/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
9/24/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/24/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
9/24/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
9/24/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
9/24/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/25/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
9/30/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/30/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
9/30/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
10/2/2025
|
Approved
|
RONALD JIMENEZ
|
|
Insulation
|
10/2/2025
|
Approved
|
RONALD JIMENEZ
|
|
Interior/Exterior Lathing
|
10/6/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Excavation/Setback/Form/Re-Bar
|
10/7/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
10/7/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
10/8/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
10/8/2025
|
Approved
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
10/9/2025
|
Approved
|
RONALD JIMENEZ
|
|
Insulation
|
10/9/2025
|
Approved
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
10/16/2025
|
Approved
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
10/16/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
10/16/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Special/Order Compliance
|
10/17/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Insulation
|
10/24/2025
|
Not Ready for Inspection
|
LUIS CCAMACHO
|
|
T-Bar Ceiling
|
10/24/2025
|
Not Ready for Inspection
|
LUIS CCAMACHO
|
|
Special/Order Compliance
|
10/28/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
T-Bar Ceiling
|
10/28/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
11/5/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
11/5/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
|
T-Bar Ceiling
|
11/5/2025
|
Approved
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
11/12/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Interior/Exterior Lathing
|
11/12/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
11/12/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Special/Order Compliance
|
11/12/2025
|
Partial Approval
|
SCOTT SOBEL
|
|
Drywall Nailing
|
11/14/2025
|
Approved
|
RONALD JIMENEZ
|
|
Interior/Exterior Lathing
|
11/14/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
11/14/2025
|
Approved
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
11/17/2025
|
Partial Approval
|
RONALD JIMENEZ
|
|
Interior/Exterior Lathing
|
11/17/2025
|
Approved
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
11/17/2025
|
Approved
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
11/25/2025
|
Approved
|
RONALD JIMENEZ
|
|
Pre-Inspection
|
12/30/2025
|
Approved
|
RONALD JIMENEZ
|
|
Special/Order Compliance
|
12/30/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Excavation/Setback/Form/Re-Bar
|
1/23/2026
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Special/Order Compliance
|
1/23/2026
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Structural Steel Frame
|
1/23/2026
|
Approved
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
2/2/2026
|
Partial Approval
|
REGINA MENDEZ
|
|
Footing/Foundation/Slab
|
2/4/2026
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
2/11/2026
|
Partial Approval
|
RONALD JIMENEZ
|
|
Final
|
3/16/2026
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Green Building Final
|
3/16/2026
|
Approved
|
RONALD JIMENEZ
|
|
Reinforced Masonry Frame
|
3/16/2026
|
Approved
|
RONALD JIMENEZ
|
|
Order to Comply
|
3/17/2026
|
Not Required
|
SEAN POMISH
|
|
Order to Comply
|
3/18/2026
|
Not Required
|
SEAN POMISH
|
|
Special/Order Compliance
|
3/20/2026
|
Approved
|
RONALD JIMENEZ
|