265 N HOMEWOOD ROAD 90049

Certificate Information: 265 N HOMEWOOD ROAD 90049

Application / Permit
21016-10002-39435
Plan Check / Job No.
B23LA14862
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO PERMIT 21016-10000-39435 TO REVISE THE FIRST AND SECOND FLOOR PLAN AND UPDATE THE WORK DESCRIPTION TO "EXTERIOR AND INTERIOR REMODEL AND ADDITION TO (E) 2-STORY SINGLE FAMILY DWELLING."
Permit Issued
Issued on 8/16/2023
Issuing Office
Current Status
CofO Issued on 4/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2023 APPLICANT
Assigned to Plan Check Engineer 8/10/2023 DANIEL YIP
Corrections Issued 8/10/2023 DANIEL YIP
Plan Check Approved 8/16/2023 DANIEL YIP
Issued 8/16/2023 APPLICANT
CofO in Progress 4/17/2025 KEVIN SARGSYAN
Permit Finaled 4/21/2025 RICHARD STEINBACH
CofO Issued 4/21/2025 RICHARD STEINBACH
Permit Finaled 4/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/14/2023 DANIEL YIP

Contact Information

Architect , ; Lic. No.: C38655 2315 W 21ST ST      LOS ANGELES, CA 90018
Contractor Hanover Builders Inc; Lic. No.: 709353-B 141 DUESENBERG DRIVE STE 6      WESTLAKE VILLAGE, CA 91362
Engineer Shah,, Kamal Rajendra; Lic. No.: C46200 28611 HASKELL CANYON RD      SANTA CLARITA, CA 91390

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/24/2023 Conditional Approval ARAM AVEDISIAN
Footing/Foundation/Slab 8/31/2023 Conditional Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 9/5/2023 No Access for Inspection KENNETH NAGLE
PLUMBING-Rough 10/24/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 10/31/2023 Partial Approval ARAM AVEDISIAN
Insulation 10/31/2023 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Partial Approval KEVIN SARGSYAN
Underground Mechanical 12/6/2023 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 1/16/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 3/15/2024 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 4/16/2025 Approved KEVIN SARGSYAN
Drywall Nailing 4/16/2025 Approved KEVIN SARGSYAN
Final 4/16/2025 OK to Issue CofO KEVIN SARGSYAN
Footing/Foundation/Slab 4/16/2025 Approved KEVIN SARGSYAN
Green Building Final 4/16/2025 Approved KEVIN SARGSYAN
Green Building Rough 4/16/2025 Approved KEVIN SARGSYAN
Smoke Detectors 4/16/2025 Approved KEVIN SARGSYAN