1907 W 84TH ST 90047

Certificate Information: 1907 W 84TH ST 90047

Application / Permit
21016-10002-18972
Plan Check / Job No.
B22LA04842
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: SUPPLEMENTAL TO PERMIT 21016-10000-18972 TO REVISE THE SCOPE OF WORK TO (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) "The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."
Permit Issued
Issued on 4/14/2022
Issuing Office
Current Status
Permit Finaled on 11/26/2024

Permit Application Status History

Submitted 3/18/2022 APPLICANT
Assigned to Plan Check Engineer 3/19/2022 DANIEL YIP
Corrections Issued 3/21/2022 DANIEL YIP
Plan Check Approved 4/13/2022 DANIEL YIP
Issued 4/14/2022 APPLICANT
Permit Finaled 11/25/2024 AMIR NAZARIAN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/22/2022 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 6/22/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/27/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 6/27/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Pre-Inspection 6/27/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/12/2022 Approved ENRIQUE MIRELES
Pre-Inspection 7/12/2022 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 8/17/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 8/17/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 3/31/2023 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 3/31/2023 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 3/31/2023 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 4/4/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/6/2023 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 4/6/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 4/6/2023 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 4/6/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/9/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 5/9/2023 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 5/9/2023 Approved ENRIQUE MIRELES
Wood Frame 5/15/2023 Approved ENRIQUE MIRELES
Insulation 5/23/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 6/26/2023 Approved ENRIQUE MIRELES
Drywall Nailing 11/25/2024 Approved AMIR NAZARIAN
Final 11/25/2024 Permit Finaled AMIR NAZARIAN
Green Building Final 11/25/2024 Approved AMIR NAZARIAN
Service/Power Release 11/25/2024 Approved AMIR NAZARIAN
Smoke Detectors 11/25/2024 Approved AMIR NAZARIAN