8500 N BALBOA BLVD NO. 100 91325

Certificate Information: 8500 N BALBOA BLVD NO. 100 91325

Application / Permit
21016-10002-09100
Plan Check / Job No.
B22LA02040
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Manufacturing
Work Description
SUPPLEMENTAL TO 21016-10000-09100 FOR STRUCTURAL RETROFIT FOR NEW HVAC EQUIPMENT SUPPORT, ACOUSTICAL UNISTRUT CEILING AND REINFORCE GLULAM WITH FRP (NO CHANGE IN FLOOR AREA) AND REVISE ADDRESS
Permit Issued
Issued on 6/10/2022
Issuing Office
Metro
Current Status
Permit Finaled on 10/18/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 STARR CHEN
Corrections Issued 3/21/2022 STARR CHEN
Quality Review Completed 3/25/2022 KEN GILL
Building Plans Picked Up 3/29/2022 APPLICANT
Applicant returned to address corrections 4/21/2022 STARR CHEN
Applicant returned to address corrections 5/12/2022 STARR CHEN
Applicant returned to address corrections 5/26/2022 STARR CHEN
Plan Check Approved 6/3/2022 STARR CHEN
Issued 6/10/2022 APPLICANT
Permit Finaled 10/17/2022 JEFFREY FULTON

Permit Application Clearance Information

No Data Available.

Contact Information

Architect , ; Lic. No.: C22710       ,
Contractor Clune Construction Company L P; Lic. No.: 732107-B 725 SOUTH FIGUEROA STREET   STE 300    LOS ANGELES, CA 90017
Engineer Toranzo,, Luis; Lic. No.: S6014 12005 ALBERS ST 222      VALLEY VILLAGE, CA 91607

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 7/7/2022 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 7/8/2022 Partial Inspection JEFFREY FULTON
T-Bar Ceiling 7/13/2022 No Access for Inspection JEFFREY FULTON
Insulation 7/25/2022 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/28/2022 Partial Inspection JEFFREY FULTON
Final 8/22/2022 Not Ready for Inspection JEFFREY FULTON
Insulation 8/22/2022 Partial Inspection JEFFREY FULTON
Smoke Detectors 8/22/2022 Approved JEFFREY FULTON
Final 8/30/2022 Partial Inspection JEFFREY FULTON
Final 10/17/2022 Permit Finaled JEFFREY FULTON