7408 W 82ND ST 90045
Certificate Information: 7408 W 82ND ST 90045
- Application / Permit
- 21016-10001-59094
- Plan Check / Job No.
- B22LA07072
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL PERMIT TO 21016-10K-59094 TO CAPTURE ELECTRICAL/ PLUMBING/ HVAC FEES ONLY.
- Permit Issued
- Issued on 4/19/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 4/19/2022 | VIVIAN LAO |
| Issued | 4/19/2022 | APPLICANT |
| Permit Finaled | 10/13/2022 | BOBBY KEY |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/25/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 4/25/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 5/9/2022 | Approved | BOBBY KEY |
| Final | 5/9/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 5/9/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 5/9/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 6/7/2022 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 6/9/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 6/9/2022 | Approved | BOBBY KEY |
| Green Building Rough | 6/9/2022 | Approved | BOBBY KEY |
| Insulation | 6/9/2022 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 6/22/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2022 | Approved | BOBBY KEY |
| Insulation | 6/22/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 8/10/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 8/10/2022 | Approved | BOBBY KEY |