2213-2215 S BURNSIDE AVE 90016

Certificate Information: 2213-2215 S BURNSIDE AVE 90016

Application / Permit
21016-10001-14403
Plan Check / Job No.
B21LA15493
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
SUP TO 21016-10000-14403 "REPAIR/REPLACE ONE HOUR FIRE RATED/SOUND RATED PARTITION BETWEEN UNITS." INTERIOR REMODEL RE-FRAME DETERIOARATED (WATER AND TERMITE DAMAGED) INTERIOR NON BEARING PARTITIONS. PROVIDE R-13 INSULATION ON EXTERIOR WALLS AND R-30 ON CEILING, NEW DRYWALL FINISH, 2 - EXHAUST FANS, 2 GRAVITY TYPE WALL FURNACES. no change to plot plan
Permit Issued
Issued on 8/31/2021
Issuing Office
Current Status
Permit Finaled on 4/26/2022

Permit Application Status History

Submitted 8/19/2021 APPLICANT
Assigned to Plan Check Engineer 8/20/2021 DANIEL SANJUAN
Plan Check Approved 8/26/2021 DANIEL SANJUAN
Issued 8/31/2021 APPLICANT
Permit Finaled 4/25/2022 JOSE AVILA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Premier Construction Consultant; Lic. No.: 1043804-B 7844 KINGBEE STREET      DOWNEY, CA 90242

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 9/14/2021 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Rough 10/6/2021 Approved JUSTIN HAWLEY
HVAC-Rough 10/6/2021 Approved JUSTIN HAWLEY
Insulation 10/6/2021 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 10/6/2021 Approved JUSTIN HAWLEY
Drywall Nailing 10/14/2021 Approved LILIANA PORTILLO
Interior/Exterior Lathing 10/14/2021 Approved LILIANA PORTILLO
Final 2/7/2022 Corrections Issued JOSE AVILA
Smoke Detectors 2/7/2022 Approved JOSE AVILA
Final 3/2/2022 Corrections Issued JOSE AVILA
Final 4/19/2022 Corrections Issued JOSE AVILA
Final 4/25/2022 Permit Finaled JOSE AVILA