1141-1149 N MANSFIELD AVE 90038

Certificate Information: 1141-1149 N MANSFIELD AVE 90038

Application / Permit
21016-10001-02161
Plan Check / Job No.
B21LA16802
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(21) Motion Picture Film or Television Tape Editing
Work Description
Supplemental to permit 21016-10000-02161 to revise use code to "Motion Picture Film" . Change of use from office, storage and food product manufacturing on first floor to media production office, including tenant improvement.
Permit Issued
Issued on 2/8/2022
Issuing Office
Current Status
Permit Finaled on 3/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 HELEN NGUYEN
Corrections Issued 9/16/2021 HELEN NGUYEN
Quality Review Completed 9/28/2021 MICHAEL PEREZ
Disabled Access Plans Picked Up 10/19/2021 APPLICANT
Applicant returned to address corrections 11/26/2021 HELEN NGUYEN
Applicant returned to address corrections 12/9/2021 HELEN NGUYEN
Applicant returned to address corrections 1/10/2022 HELEN NGUYEN
Plan Check Approved 1/18/2022 HELEN NGUYEN
Issued 2/8/2022 APPLICANT
Building Plans Picked Up 2/16/2022 APPLICANT
Permit Finaled 3/31/2023 KATY RAMIREZ

Permit Application Clearance Information

ZA Case Cleared 10/12/2021 ANACANY HURTADO
ZA Case Cleared 10/12/2021 ANACANY HURTADO
Sewer availability Cleared 10/13/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 10/15/2021 THOMAS LANG
DAS Clearance Cleared 11/23/2021 HELEN NGUYEN

Contact Information

Architect Brennan,, Ross A; Lic. No.: C27858 7008 SANTA MONICA BLVD      HOLLYWOOD, CA 90038
Contractor Sierra Pacific Constructors Inc; Lic. No.: 433163-B 22212 VENTURA BLVD      WOODLAND HILLS, CA 91364
Engineer Cairo,, Marcelo Daniel; Lic. No.: S4483 10750 SKYDANCE DR      HIGHLANDS RANCH, CO 80126

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 2/17/2022 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 3/7/2022 Partial Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 3/9/2022 Partial Approval KATY RAMIREZ
Drywall Nailing 3/17/2022 Partial Approval KATY RAMIREZ
Wood Frame 3/17/2022 Approved KATY RAMIREZ
Drywall Nailing 3/22/2022 Approved JONATHAN QUACH
Light Gage Steel Frame 4/27/2022 Not Ready for Inspection KATY RAMIREZ
T-Bar Ceiling 4/27/2022 Approved KATY RAMIREZ
Special/Order Compliance 6/9/2022 Partial Inspection KATY RAMIREZ
Special/Order Compliance 6/15/2022 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 7/28/2022 Partial Approval KATY RAMIREZ
Final 3/24/2023 Partial Inspection KATY RAMIREZ
Smoke Detectors 3/24/2023 Approved KATY RAMIREZ