1095 S GENESEE AVE 90019
Certificate Information: 1095 S GENESEE AVE 90019
- Application / Permit
- 21016-10000-59413
- Plan Check / Job No.
- B21LA24389
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- INTERIOR REMODEL. ADDITION OF 2 BATHROOMS + ONE POWDER BATHROOM TO EACH OF THE TWO UNITS. FRAME PLUMBING WALLS, NO STRUCTURAL CHANGE.
- Permit Issued
- Issued on 3/16/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/20/2023
Permit Application Status History
| Submitted | 12/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2022 | FERNANDO FLORES |
| Corrections Issued | 1/8/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 2/5/2022 | FERNANDO FLORES |
| Plan Check Approved | 3/10/2022 | JOSEPH RAFOLS |
| Issued | 3/16/2022 | APPLICANT |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| Permit Finaled | 10/19/2023 | JOSE AVILA |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/3/2022 | AMAAN MALIK |
| Tenant Habitability Plan | Cleared | 2/3/2022 | MICHAEL SOTO |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2022 | AMAAN MALIK |
| City Hist. Cultural Monument | Cleared | 3/8/2022 | MAX LODER |
| Historic monument | Cleared | 3/8/2022 | MAX LODER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | Not Ready for Inspection | JOSE AVILA |
| Wood Frame | 11/22/2022 | Not Ready for Inspection | MICHAEL LEWIS |
| Wood Frame | 12/6/2022 | Partial Approval | JOSE AVILA |
| Insulation | 12/27/2022 | Partial Approval | JOSE AVILA |
| Drywall Nailing | 1/17/2023 | Partial Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 1/17/2023 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 1/17/2023 | Partial Inspection | SCOTT FINNILA |
| Deputy Wood Construction | 2/13/2023 | Conditional Approval | JOSE AVILA |
| Wood Frame | 2/24/2023 | Approved | JOSE AVILA |
| Insulation | 3/3/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 3/29/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 3/29/2023 | Corrections Issued | JOHN KIDWELL |
| Special/Order Compliance | 7/13/2023 | Corrections Issued | JOSE AVILA |
| Final | 10/19/2023 | Permit Finaled | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 10/19/2023 | SGSOV No Gas | JOSE AVILA |
| Smoke Detectors | 10/19/2023 | Approved | JOSE AVILA |