4423 W FINLEY AVE 90027
Certificate Information: 4423 W FINLEY AVE 90027
- Application / Permit
- 21016-10000-59393
- Plan Check / Job No.
- B21LA24352
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE INTO AN ADU
- Permit Issued
- Issued on 3/24/2022
- Issuing Office
- Current Status
- CofO Issued on 10/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2022 | TSE MING HUANG |
| Plan Check Approved | 2/7/2022 | SINA KHOSRAVI |
| Issued | 3/24/2022 | APPLICANT |
| Building Plans Picked Up | 5/5/2022 | APPLICANT |
| CofO in Progress | 9/9/2022 | JOSEPH MCGARRY |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
| CofO Issued | 10/1/2022 | DEROLD HAUFF |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2022 | CINDY QI |
| Sewer availability | Cleared | 1/24/2022 | CINDY QI |
Contact Information
| Contractor | B T R Construction Inc; Lic. No.: 875887-B | 5525 MELVIN AVE TARZANA, CA 91356 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/8/2022 | Approved | CRAIG DAVIS |
| Sewer | 4/8/2022 | Approved | CRAIG DAVIS |
| Underground Mechanical | 4/8/2022 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 5/6/2022 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/6/2022 | Approved | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 5/6/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 5/6/2022 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/6/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 6/8/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 6/8/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/8/2022 | Approved | JOSEPH MCGARRY |
| Shower Pan | 6/8/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/14/2022 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 6/14/2022 | Approved | JOSEPH MCGARRY |
| Gas Test | 6/14/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/14/2022 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 7/15/2022 | Approved | JOSEPH MCGARRY |
| Final | 8/24/2022 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 8/24/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 8/24/2022 | Approved | JOSEPH MCGARRY |
| Final | 9/6/2022 | OK to Issue CofO | JOSEPH MCGARRY |