4553 S GLENCOE AVE 90292

Certificate Information: 4553 S GLENCOE AVE 90292

Application / Permit
21016-10000-59383
Plan Check / Job No.
B21LA24335
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Clinic
Work Description
ePlan Change of use from office to ambulatory surgery center (less than 24 hrs. stay), IMAGING SUITE, AND ADMINISTRATION CENTER LOCATED ON THE GROUND FLOOR. NO CHANGE IN OCCUPANCY. Fire sprinkler system reqd.
Permit Issued
Issued on 7/14/2022
Issuing Office
Current Status
CofO Issued on 10/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2022 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 ZAW HAN
Corrections Issued 1/20/2022 ZAW HAN
Quality Review Completed 1/28/2022 SAI KHUM
Applicant returned to address corrections 4/28/2022 ZAW HAN
Applicant returned to address corrections 5/27/2022 ZAW HAN
Applicant returned to address corrections 6/24/2022 ZAW HAN
Plan Check Approved 7/1/2022 ZAW HAN
Issued 7/14/2022 APPLICANT
TCO Issued (Expire Date: 01-31-2024) 8/4/2023 DAVID TSAU
TCO Issued (Expire Date: 07-16-2024) 1/18/2024 DAVID TSAU
TCO Issued (Expire Date: 01-05-2025) 7/9/2024 DAVID TSAU
TCO Issued (Expire Date: 01-19-2025) 7/23/2024 DAVID TSAU
CofO in Progress 10/4/2024 GRANT WOODS
CofO in Progress 10/4/2024 GRANT WOODS
Permit Finaled 10/4/2024 HENRY BAGHDASSARIAN
Permit Finaled 10/4/2024 HENRY BAGHDASSARIAN
CofO Issued 10/4/2024 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Green Code Cleared 4/7/2022 AARON COSTA
"Q" conditions Cleared 4/27/2022 RYAN LY
Coastal Zone Cleared 4/27/2022 RYAN LY
ZA Case Cleared 4/27/2022 RYAN LY
Eng Process Fee Ord 176,300 Cleared 5/9/2022 SAUL GARCIA
Sewer availability Cleared 5/9/2022 SAUL GARCIA
DAS Clearance Cleared 5/12/2022 SAI KHUM
Specific Plan Cleared 6/16/2022 FREDDY GARCIA

Contact Information

Architect Gresko,, John C; Lic. No.: NA37856       ,
Contractor Cannon Building Services Inc; Lic. No.: 553842-B 1861 E MIRALOMA AVE      PLACENTIA, CA 92870
Engineer Young,, Roger Paul; Lic. No.: S3623 31812 VIA COYOTE      TRABUCO CANYON, CA 92679

Inspector Information

DANIEL ARMENTA, (310) 914-3925 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/3/2022 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 8/3/2022 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 8/4/2022 Approved GRANT WOODS
Deputy Reinf. Concrete 8/4/2022 Approved GRANT WOODS
Excavation/Setback/Form/Re-Bar 8/4/2022 Partial Approval GRANT WOODS
Deputy Drilled-In Anchors 8/5/2022 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 8/5/2022 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 8/10/2022 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 8/11/2022 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 8/12/2022 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 8/18/2022 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 8/19/2022 Conditional Approval ALAN NOVAK
Excavation/Setback/Form/Re-Bar 8/19/2022 Partial Inspection ALAN NOVAK
Pre-Inspection 8/30/2022 Approved GRANT WOODS
Deputy Steel/Welding 9/13/2022 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 9/14/2022 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 9/16/2022 Approved GRANT WOODS
Deputy Steel/Welding 9/16/2022 Approved GRANT WOODS
Excavation/Setback/Form/Re-Bar 9/16/2022 Partial Approval GRANT WOODS
Deputy Reinf. Concrete 9/19/2022 Conditional Approval GRANT WOODS
Light Gage Steel Frame 10/7/2022 Not Ready for Inspection GRANT WOODS
Deputy Drilled-In Anchors 10/17/2022 Conditional Approval GRANT WOODS
Deputy Steel/Welding 10/18/2022 Conditional Approval GRANT WOODS
Drywall Nailing 10/18/2022 Partial Approval GRANT WOODS
Drywall Nailing 10/24/2022 Partial Approval GRANT WOODS
Drywall Nailing 10/31/2022 Partial Inspection GRANT WOODS
Light Gage Steel Frame 10/31/2022 Partial Inspection GRANT WOODS
Structural Steel Frame 10/31/2022 Partial Inspection GRANT WOODS
Drywall Nailing 11/3/2022 Partial Approval ALAN NOVAK
Deputy Steel/Welding 11/8/2022 Conditional Approval GRANT WOODS
Deputy Steel/Welding 11/9/2022 Conditional Approval GRANT WOODS
Drywall Nailing 11/9/2022 Partial Approval GRANT WOODS
Drywall Nailing 11/21/2022 Partial Approval NICK LAROCCA
Structural Steel Frame 11/21/2022 Partial Inspection NICK LAROCCA
Wood Frame 11/21/2022 Partial Inspection NICK LAROCCA
Deputy Fireproofing 11/22/2022 Conditional Approval ALAN NOVAK
Drywall Nailing 11/30/2022 Partial Approval GRANT WOODS
Deputy Fireproofing 12/1/2022 Conditional Approval GRANT WOODS
Drywall Nailing 12/7/2022 Partial Approval GRANT WOODS
Light Gage Steel Frame 12/7/2022 Partial Approval GRANT WOODS
Light Gage Steel Frame 12/13/2022 Partial Approval GRANT WOODS
Light Gage Steel Frame 12/19/2022 Partial Approval GRANT WOODS
Light Gage Steel Frame 1/10/2023 Not Ready for Inspection GRANT WOODS
Light Gage Steel Frame 1/13/2023 Partial Approval GRANT WOODS
Footing/Foundation/Slab 2/13/2023 Not Ready for Inspection GRANT WOODS
Deputy Reinf. Concrete 2/14/2023 Conditional Approval GRANT WOODS
Light Gage Steel Frame 2/16/2023 Partial Approval GRANT WOODS
Deputy Reinf. Concrete 2/22/2023 Conditional Approval SHAVONNE ESPINOZA
Deputy Drilled-In Anchors 2/23/2023 Conditional Approval GRANT WOODS
Deputy Fireproofing 2/23/2023 Conditional Approval GRANT WOODS
Drywall Nailing 2/28/2023 Partial Approval GRANT WOODS
Light Gage Steel Frame 2/28/2023 Partial Approval GRANT WOODS
Deputy Reinf. Concrete 3/8/2023 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 3/13/2023 Conditional Approval GRANT WOODS
Light Gage Steel Frame 3/14/2023 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 3/20/2023 Not Ready for Inspection GRANT WOODS
Light Gage Steel Frame 3/24/2023 Approved AMANUEL BERHE
Deputy Drilled-In Anchors 3/28/2023 Conditional Approval GRANT WOODS
Footing/Foundation/Slab 4/5/2023 Partial Approval GRANT WOODS
Deputy Reinf. Masonry 4/14/2023 Conditional Approval GRANT WOODS
Deputy Steel/Welding 4/14/2023 Approved GRANT WOODS
Masonry Wall/Backfill 4/14/2023 Not Ready for Inspection GRANT WOODS
Deputy Drilled-In Anchors 4/19/2023 Conditional Approval GRANT WOODS
Deputy Reinf. Masonry 4/20/2023 Conditional Approval AMANUEL BERHE
Deputy Steel/Welding 4/26/2023 Conditional Approval GRANT WOODS
Footing/Foundation/Slab 4/28/2023 Conditional Approval AMANUEL BERHE
Excavation/Setback/Form/Re-Bar 5/1/2023 Partial Approval GRANT WOODS
Light Gage Steel Frame 5/1/2023 Not Ready for Inspection GRANT WOODS
T-Bar Ceiling 5/1/2023 Not Ready for Inspection GRANT WOODS
Deputy Reinf. Concrete 5/2/2023 Conditional Approval GRANT WOODS
Deputy Steel/Welding 5/10/2023 Conditional Approval DAVID TSAU
Deputy Steel/Welding 5/12/2023 Conditional Approval GRANT WOODS
Structural Steel Frame 5/12/2023 Partial Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 5/23/2023 Partial Approval GRANT WOODS
Light Gage Steel Frame 5/23/2023 Partial Approval GRANT WOODS
Light Gage Steel Frame 5/30/2023 Partial Approval GRANT WOODS
Drywall Nailing 6/1/2023 Partial Approval GRANT WOODS
Light Gage Steel Frame 6/5/2023 Conditional Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 6/9/2023 Partial Approval GRANT WOODS
Deputy Fireproofing 6/12/2023 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 6/14/2023 Conditional Approval GRANT WOODS
T-Bar Ceiling 6/16/2023 Not Ready for Inspection GRANT WOODS
T-Bar Ceiling 6/22/2023 Partial Approval GRANT WOODS
Light Gage Steel Frame 7/3/2023 Partial Approval GRANT WOODS
Final 7/14/2023 Partial Inspection GRANT WOODS
Green Building Final 7/14/2023 Not Ready for Inspection GRANT WOODS
METHANE-Final 7/14/2023 Not Ready for Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 7/14/2023 SGSOV Not Ready GRANT WOODS
Smoke Detectors 7/14/2023 Not Ready for Inspection GRANT WOODS
Final 7/20/2023 Partial Inspection GRANT WOODS
Green Building Final 7/20/2023 Not Ready for Inspection GRANT WOODS
METHANE-Final 7/20/2023 Not Ready for Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 7/20/2023 SGSOV Not Ready GRANT WOODS
Smoke Detectors 7/20/2023 Not Ready for Inspection GRANT WOODS
T-Bar Ceiling 8/15/2023 Not Ready for Inspection GRANT WOODS
T-Bar Ceiling 8/17/2023 Partial Approval GRANT WOODS
Final 11/2/2023 Partial Inspection GRANT WOODS
Green Building Final 11/2/2023 Not Ready for Inspection GRANT WOODS
METHANE-Final 11/2/2023 Not Ready for Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Not Ready GRANT WOODS
Smoke Detectors 11/2/2023 Not Ready for Inspection GRANT WOODS
Special/Order Compliance 1/3/2024 Approved GRANT WOODS
Deputy Steel/Welding 1/16/2024 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 1/18/2024 Conditional Approval GRANT WOODS
Light Gage Steel Frame 1/23/2024 Partial Approval GRANT WOODS
Light Gage Steel Frame 2/26/2024 Partial Approval GRANT WOODS
Special/Order Compliance 2/26/2024 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 3/6/2024 Partial Approval GRANT WOODS
Drywall Nailing 3/11/2024 Partial Approval GRANT WOODS
Drywall Nailing 3/21/2024 Partial Approval GRANT WOODS
Drywall Nailing 3/29/2024 Partial Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 4/3/2024 Not Ready for Inspection GRANT WOODS
Deputy Reinf. Concrete 4/4/2024 Conditional Approval GRANT WOODS
Drywall Nailing 4/16/2024 Approved GRANT WOODS
T-Bar Ceiling 5/8/2024 Partial Approval ALAN NOVAK
Light Gage Steel Frame 5/9/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 5/15/2024 Approved ALAN NOVAK
Special/Order Compliance 6/24/2024 Partial Inspection GRANT WOODS
Final 7/3/2024 Corrections Issued GRANT WOODS
Green Building Final 7/3/2024 Not Ready for Inspection GRANT WOODS
METHANE-Final 7/3/2024 Not Ready for Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 7/3/2024 SGSOV Not Ready GRANT WOODS
Smoke Detectors 7/3/2024 Not Ready for Inspection GRANT WOODS
Final 7/12/2024 Not Ready for Inspection GRANT WOODS
Green Building Final 7/12/2024 Not Ready for Inspection GRANT WOODS
METHANE-Final 7/12/2024 Not Ready for Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 7/12/2024 SGSOV Not Ready GRANT WOODS
Smoke Detectors 7/12/2024 Approved GRANT WOODS
Deputy Reinf. Concrete 9/5/2024 Conditional Approval FARHAD DADBIN
Deputy Reinf. Concrete 9/6/2024 Conditional Approval GRANT WOODS
Final 9/18/2024 Not Ready for Inspection GRANT WOODS
Green Building Final 9/18/2024 Approved GRANT WOODS
METHANE-Final 9/18/2024 Approved GRANT WOODS
SGSOV-Seismic Gas S/O Valve 9/18/2024 SGSOV Approved GRANT WOODS
Final 10/4/2024 Conditional Approval GRANT WOODS