5407 E RANGE VIEW AVE 90042

Certificate Information: 5407 E RANGE VIEW AVE 90042

Application / Permit
21016-10000-59355
Plan Check / Job No.
B21LA24297
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached Garage to ADU PER GCS65852.2(e)(1)(A).
Permit Issued
Issued on 4/28/2022
Issuing Office
Current Status
CofO Issued on 3/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2022 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 RAHEL BEYENE
Corrections Issued 1/13/2022 RAHEL BEYENE
Plan Check Approved 3/1/2022 RICARDO RAMIREZ
Building Plans Picked Up 3/2/2022 APPLICANT
Issued 4/28/2022 APPLICANT
CofO in Progress 3/1/2023 CRAIG VAUGHAN
Permit Finaled 3/2/2023 DEROLD HAUFF
CofO Issued 3/2/2023 DEROLD HAUFF
Permit Finaled 3/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/26/2022 JEANETTE VONG
Sewer availability Cleared 1/26/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/7/2022 JEANETTE VONG

Contact Information

Architect Allen,, Rachel M; Lic. No.: C28585 423 GIN LING WAY   RADAR, INC.    LOS ANGELES, CA 90012
Contractor Shik Builders Inc; Lic. No.: 994709-B 20305 OXNARD STREET      WOODLAND HILLS, CA 91367
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/17/2022 Not Ready for Inspection CRAIG VAUGHAN
Underground Mechanical 5/17/2022 Partial Approval CRAIG VAUGHAN
Underground Mechanical 5/20/2022 Approved AMY COLIN
Footing/Foundation/Slab 6/1/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 6/30/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/30/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 6/30/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 6/30/2022 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/7/2022 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 7/7/2022 Corrections Issued SCOTT FINNILA
Green Building Rough 7/7/2022 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 7/7/2022 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 7/25/2022 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 7/25/2022 Partial Approval CRAIG VAUGHAN
Green Building Rough 7/25/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 7/25/2022 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 7/26/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 7/26/2022 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 7/29/2022 Partial Approval CRAIG VAUGHAN
Green Building Rough 7/29/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 7/29/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 8/4/2022 Approved CRAIG VAUGHAN
Insulation 8/4/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 8/4/2022 Partial Approval CRAIG VAUGHAN
Shower Pan 8/4/2022 Approved CRAIG VAUGHAN
Drywall Nailing 8/8/2022 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 8/8/2022 Partial Approval KATHRYN BUTTERWORTH
Final 2/1/2023 Corrections Issued CRAIG VAUGHAN
Green Building Final 2/1/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/1/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 2/1/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 2/14/2023 Approved CRAIG VAUGHAN
Final 2/14/2023 Corrections Issued CRAIG VAUGHAN
HVAC-Final 2/14/2023 Approved CRAIG VAUGHAN
PLUMBING-Final 2/14/2023 Approved CRAIG VAUGHAN
Final 2/28/2023 OK to Issue CofO CRAIG VAUGHAN