843 N NORTH SPRING ST 90012
Certificate Information: 843 N NORTH SPRING ST 90012
- Application / Permit
- 21016-10000-59257
- Plan Check / Job No.
- B21LA24157
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ePLAN. DEFERRED SUBMITTAL FOR 19014-10000-03188 EXTERIOR METAL STUD
- Permit Issued
- Issued on 5/20/2022
- Issuing Office
- Current Status
- Permit Finaled on 1/26/2024
Permit Application Status History
| Submitted | 12/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2022 | KEVIN MORALES |
| Corrections Issued | 1/27/2022 | KEVIN MORALES |
| Quality Review Completed | 2/2/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 4/11/2022 | KEVIN MORALES |
| Plan Check Approved | 4/22/2022 | KEVIN MORALES |
| Issued | 5/20/2022 | APPLICANT |
| Permit Finaled | 1/26/2024 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Shawmut Design And Construction; Lic. No.: 747583-B | 560 HARRISON AVENUE BOSTON, MA 02118 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 5/31/2022 | Partial Approval | MARK FERRARI |
| Light Gage Steel Frame | 5/31/2022 | Partial Approval | MARK FERRARI |
| Drywall Nailing | 6/23/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Light Gage Steel Frame | 6/23/2022 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 7/12/2022 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 7/12/2022 | Partial Approval | MARK FERRARI |
| Light Gage Steel Frame | 7/12/2022 | Partial Approval | MARK FERRARI |
| Insulation | 8/31/2022 | Approved | DARRYL ARNOLD |
| Light Gage Steel Frame | 12/15/2022 | Partial Approval | MARK FERRARI |
| Pre-Inspection | 12/15/2022 | Partial Inspection | ALAN MORELOS |