700 N ROBINSON ST 90026
Certificate Information: 700 N ROBINSON ST 90026
- Application / Permit
- 21016-10000-59231
- Plan Check / Job No.
- B21LA24128
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story Seismic Retrofit per LABC Chapter 93: INSTALL (1) SPECIAL CANTILEVERED COLUMN
- Permit Issued
- Issued on 8/9/2022
- Issuing Office
- Current Status
- CofC Issued on 2/22/2023
Permit Application Status History
| Submitted | 1/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2022 | BIDYUT RATH |
| Corrections Issued | 2/7/2022 | BIDYUT RATH |
| Quality Review Completed | 2/14/2022 | SAI KHUM |
| Applicant returned to address corrections | 4/7/2022 | BIDYUT RATH |
| Plan Check Approved | 6/2/2022 | BIDYUT RATH |
| Issued | 8/9/2022 | APPLICANT |
| OK for CofC | 11/16/2022 | DARRYL ARNOLD |
| CofC Issued | 2/22/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/4/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | 636 NORTH FORMOSA AVENUE LOS ANGELES, CA 90036 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/30/2022 | Corrections Issued | DARRYL ARNOLD |
| Deputy Steel/Welding | 9/8/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 9/12/2022 | Conditional Approval | BRUCE CAMPBELL |
| Excavation/Setback/Form/Re-Bar | 9/14/2022 | Approved | BRUCE CAMPBELL |
| Structural Steel Frame | 9/14/2022 | Approved | BRUCE CAMPBELL |
| Wood Frame | 9/14/2022 | Approved | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 9/20/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/13/2022 | Conditional Approval | DARRYL ARNOLD |
| Pre-Inspection | 10/26/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 11/16/2022 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 11/16/2022 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Approved | DARRYL ARNOLD |