956 S ELDEN AVE 90006
Certificate Information: 956 S ELDEN AVE 90006
- Application / Permit
- 21016-10000-59229
- Plan Check / Job No.
- B21LA24124
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Soft Story retrofit using 3 SCCS & 1 Plywood Shear Wall
- Permit Issued
- Issued on 5/26/2022
- Issuing Office
- Current Status
- CofC Issued on 6/13/2023
Permit Application Status History
| Submitted | 1/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2022 | JESSE VIDUYA |
| Corrections Issued | 1/27/2022 | JESSE VIDUYA |
| Quality Review Completed | 2/8/2022 | SAI KHUM |
| Applicant returned to address corrections | 3/1/2022 | JESSE VIDUYA |
| Applicant returned to address corrections | 3/8/2022 | JESSE VIDUYA |
| Applicant returned to address corrections | 3/18/2022 | JESSE VIDUYA |
| Plan Check Approved | 3/22/2022 | JESSE VIDUYA |
| Issued | 5/26/2022 | APPLICANT |
| OK for CofC | 1/26/2023 | DARRYL ARNOLD |
| CofC Issued | 6/13/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/3/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Cal Retrofit; Lic. No.: 1022167-B | 19528 VENTURA BLVD #300 TARZANA, CA 91356 |
| Engineer | Yiu,, Siu Fung; Lic. No.: S5801 | PO BOX 5143 EL MONTE, CA 91734 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/21/2022 | Corrections Issued | DARRYL ARNOLD |
| Pre-Inspection | 6/22/2022 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 8/19/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 8/23/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 8/23/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 8/23/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 8/24/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/29/2022 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 8/29/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 8/31/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 8/31/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 9/7/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 9/8/2022 | Partial Approval | BRUCE CAMPBELL |
| Deputy Wood Construction | 9/13/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 9/15/2022 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 9/27/2022 | Approved | DARRYL ARNOLD |
| Final | 10/31/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 10/31/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 1/26/2023 | OK for CofC | DARRYL ARNOLD |
| Special/Order Compliance | 2/10/2023 | No Access for Inspection | DARRYL ARNOLD |