6612 1/2 S 3RD AVE 90043

Certificate Information: 6612 1/2 S 3RD AVE 90043

Application / Permit
21016-10000-59148
Plan Check / Job No.
B21LA24064
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING STORAGE AND PORTION OF EX. GARAGE TO ACCESSORY DWELLING UNIT. WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
Permit Issued
Issued on 3/30/2022
Issuing Office
Current Status
CofO Issued on 9/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 DANIEL SANJUAN
Corrections Issued 12/29/2021 DANIEL SANJUAN
Plan Check Approved 3/24/2022 GEORGE ALVAREZ
Issued 3/30/2022 APPLICANT
Building Plans Picked Up 3/31/2022 APPLICANT
CofO in Progress 7/1/2022 ENRIQUE MIRELES
CofO in Progress 7/1/2022 ENRIQUE MIRELES
Permit Finaled 9/11/2022 DEROLD HAUFF
CofO Issued 9/11/2022 DEROLD HAUFF
Permit Finaled 9/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/3/2022 WALLIE JONG
Sewer availability Cleared 1/3/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/5/2022 WALLIE JONG
Construction near power lines Cleared 3/24/2022 JOHN BACON
Construction within easement Cleared 3/24/2022 JOHN BACON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/22/2022 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 5/4/2022 Approved ENRIQUE MIRELES
Insulation 5/13/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/13/2022 Approved ENRIQUE MIRELES
Shower Pan 5/13/2022 Approved ENRIQUE MIRELES
Drywall Nailing 5/23/2022 Approved ANTHONY EGSON
Green Building Rough 5/23/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 5/23/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 6/27/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Final 6/27/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 6/27/2022 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 6/27/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 6/27/2022 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/1/2022 Approved ENRIQUE MIRELES
Final 7/1/2022 OK to Issue CofO ENRIQUE MIRELES
Green Building Final 7/1/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/1/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 7/1/2022 Approved ENRIQUE MIRELES