7408 W 82ND ST 90045
Certificate Information: 7408 W 82ND ST 90045
- Application / Permit
- 21016-10000-59094
- Plan Check / Job No.
- B21LA24024
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 3/3/2022
- Issuing Office
- Current Status
- CofO Issued on 11/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2021 | VIVIAN LAO |
| Corrections Issued | 12/27/2021 | VIVIAN LAO |
| Plan Check Approved | 2/27/2022 | KEVIN MORALES |
| Issued | 3/3/2022 | APPLICANT |
| CofO in Progress | 11/9/2022 | BOBBY KEY |
| Permit Finaled | 11/15/2022 | DANIEL ORRANTE |
| CofO Issued | 11/15/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/15/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2021 | STEVEN JIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2021 | STEVEN JIN |
| Sewer availability | Cleared | 12/30/2021 | STEVEN JIN |
| Grading Pre-Inspection | Cleared | 1/7/2022 | VASIL MIHALEV |
| Specific Plan | Cleared | 1/18/2022 | PETE EYRE |
| Miscellaneous | Cleared | 1/25/2022 | HISASHI KOBAYAKAWA |
| Construction within easement | Cleared | 2/26/2022 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/23/2022 | Partial Inspection | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 4/1/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 4/1/2022 | Approved | BOBBY KEY |
| Pre-Inspection | 4/15/2022 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 4/15/2022 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 4/20/2022 | Corrections Issued | BOBBY KEY |
| Drywall Nailing | 8/11/2022 | Approved | BOBBY KEY |
| Final | 8/11/2022 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 8/11/2022 | Approved | BOBBY KEY |
| Smoke Detectors | 8/11/2022 | No Access for Inspection | BOBBY KEY |
| Wood Frame | 8/11/2022 | Approved | BOBBY KEY |
| Final | 10/13/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 10/13/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/13/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 10/13/2022 | Approved | BOBBY KEY |
| Final | 11/4/2022 | Corrections Issued | ANDREW NAVE |
| Final | 11/9/2022 | OK to Issue CofO | BOBBY KEY |