5784 ZELZAH AVE 91316
Certificate Information: 5784 ZELZAH AVE 91316
- Application / Permit
- 21016-10000-59093
- Plan Check / Job No.
- B21LA24023
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert (E) Garage to ADU per Ordinance
- Permit Issued
- Issued on 1/25/2022
- Issuing Office
- Current Status
- CofO Issued on 9/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2021 | HERNAN ARREOLA |
| Corrections Issued | 12/29/2021 | HERNAN ARREOLA |
| Plan Check Approved | 1/19/2022 | HERNAN ARREOLA |
| Issued | 1/25/2022 | APPLICANT |
| CofO in Progress | 8/19/2022 | SEAN HAUPT |
| CofO Issued | 9/21/2022 | MICHAEL SMITH |
| Permit Finaled | 9/21/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/10/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2022 | CARLOS AGUILERA |
| Construction within easement | Cleared | 1/14/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/24/2022 | Not Ready for Inspection | SEAN HAUPT |
| Sewer | 2/24/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 2/24/2022 | Approved | SEAN HAUPT |
| Wood Frame | 3/23/2022 | Partial Approval | SEAN HAUPT |
| Interior/Exterior Lathing | 4/11/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 4/14/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 4/14/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 4/14/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 4/14/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 4/14/2022 | Approved | SEAN HAUPT |
| Insulation | 4/27/2022 | Approved | MORRIS JACKSON |
| Drywall Nailing | 5/9/2022 | No Access for Inspection | MORRIS JACKSON |
| Drywall Nailing | 5/17/2022 | Approved | SEAN HAUPT |
| Shower Pan | 5/17/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 5/26/2022 | Approved | SEAN HAUPT |
| Final | 8/15/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 8/15/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 8/15/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 8/15/2022 | Approved | SEAN HAUPT |
| Final | 8/19/2022 | OK to Issue CofO | SEAN HAUPT |
| Service/Power Release | 8/19/2022 | Approved | SEAN HAUPT |