6411 W WARING AVE 90038

Certificate Information: 6411 W WARING AVE 90038

Application / Permit
21016-10000-59001
Plan Check / Job No.
B21LA23978
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert (E) garage and addition to create ADU Per GCS 65852.2
Permit Issued
Issued on 9/13/2022
Issuing Office
Current Status
CofO Issued on 12/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2021 APPLICANT
Assigned to Plan Check Engineer 12/28/2021 ZAW HAN
Corrections Issued 12/29/2021 HERNAN ARREOLA
Plan Check Approved 8/6/2022 ZAW HAN
Issued 9/13/2022 APPLICANT
CofO in Progress 10/20/2023 STUART CHAPMAN
Permit Finaled 12/27/2023 DEROLD HAUFF
CofO Issued 12/27/2023 DEROLD HAUFF
Permit Finaled 12/27/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/19/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 5/31/2022 CINDY QI
Sewer availability Cleared 5/31/2022 CINDY QI
Construction within easement Cleared 7/8/2022 TINA MIRANDA

Contact Information

Contractor L A Developing Inc; Lic. No.: 1083426-B 2926 CUDAHY STREET      HUNTINGTON PARK, CA 90255
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/21/2022 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 9/21/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/27/2022 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 9/27/2022 SGSOV Not Ready JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 9/29/2022 Partial Approval JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 10/7/2022 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 10/7/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/7/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 10/11/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/11/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 10/13/2022 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 10/13/2022 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/17/2022 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/17/2022 Conditional Approval JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 10/19/2022 Conditional Approval JOAQUIN GREENOUGH
Deputy Wood Construction 10/27/2022 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Partial Approval JOAQUIN GREENOUGH
Green Building Rough 11/2/2022 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Rough 11/2/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 11/2/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Conditional Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/2/2023 Approved JOAQUIN GREENOUGH
METHANE-Rough 2/8/2023 Approved JOAQUIN GREENOUGH
Special/Order Compliance 2/8/2023 Approved JOAQUIN GREENOUGH
Wood Frame 2/8/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 2/16/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Special/Order Compliance 2/16/2023 Approved JOAQUIN GREENOUGH
Wood Frame 2/16/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 2/17/2023 Conditional Approval JOAQUIN GREENOUGH
Insulation 2/27/2023 Approved JOAQUIN GREENOUGH
Drywall Nailing 3/8/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 3/13/2023 Approved BRIAN SULLIVAN
Final 7/20/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 7/20/2023 Approved JOAQUIN GREENOUGH
Green Building Rough 7/20/2023 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 7/20/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 7/20/2023 Approved JOAQUIN GREENOUGH
Wood Frame 7/20/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Final 7/28/2023 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Approved STUART CHAPMAN
Wood Frame 7/28/2023 Approved STUART CHAPMAN
Verify Rec and Parks Fee Memo 7/31/2023 No Access for Inspection BRIAN SULLIVAN
Final 9/25/2023 Corrections Issued JOAQUIN GREENOUGH
Final 10/19/2023 OK to Issue CofO STUART CHAPMAN