3466 S GREENWOOD AVE 90066

Certificate Information: 3466 S GREENWOOD AVE 90066

Application / Permit
21016-10000-58992
Plan Check / Job No.
B21LA23974
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert existing . attached garage into an ADU per attached adu state law.
Permit Issued
Issued on 3/9/2022
Issuing Office
Current Status
CofO Issued on 10/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2021 APPLICANT
Assigned to Plan Check Engineer 12/28/2021 CARLOS MONTES
Corrections Issued 12/29/2021 CARLOS MONTES
Applicant returned to address corrections 2/7/2022 CARLOS MONTES
Plan Check Approved 2/10/2022 CARLOS MONTES
Issued 3/9/2022 APPLICANT
CofO in Progress 10/21/2022 JESUS RODRIGUEZ
Permit Finaled 10/28/2022 DANIEL ORRANTE
CofO Issued 10/28/2022 DANIEL ORRANTE
Permit Finaled 10/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/10/2022 DINAH GARIN
Sewer availability Cleared 1/10/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/19/2022 DINAH GARIN

Contact Information

Architect Gelfat,, James Evan; Lic. No.: C19847 10748 FLAXTON ST      CULVER CITY, CA 90230
Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/1/2022 Corrections Issued PATRICK QUALEY
Gas Test 7/1/2022 Not Ready for Inspection PATRICK QUALEY
PLUMBING-Rough 7/1/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Rough 7/15/2022 Not Ready for Inspection PATRICK QUALEY
Pre-Inspection 7/15/2022 Partial Inspection PATRICK QUALEY
ELECTRICAL-Rough 7/22/2022 Corrections Issued PATRICK QUALEY
Gas Test 7/22/2022 Not Ready for Inspection PATRICK QUALEY
PLUMBING-Rough 7/22/2022 Not Ready for Inspection PATRICK QUALEY
ELECTRICAL-Rough 7/29/2022 Approved JOHNNY MIRANDA
Gas Test 7/29/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 7/29/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 8/3/2022 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 8/3/2022 Approved JESUS RODRIGUEZ
Green Building Rough 8/3/2022 Approved JESUS RODRIGUEZ
HVAC-Final 8/3/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 8/3/2022 Approved JESUS RODRIGUEZ
Insulation 8/3/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/3/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/5/2022 Approved JESUS RODRIGUEZ
Shower Pan 8/5/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 8/10/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/10/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 9/12/2022 Approved JESUS RODRIGUEZ
Final 9/12/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 9/12/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 9/12/2022 Approved JESUS RODRIGUEZ
Final 10/21/2022 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 10/21/2022 Approved JESUS RODRIGUEZ
HVAC-Final 10/21/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 10/21/2022 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 10/21/2022 Approved JESUS RODRIGUEZ