3466 S GREENWOOD AVE 90066
Certificate Information: 3466 S GREENWOOD AVE 90066
- Application / Permit
- 21016-10000-58992
- Plan Check / Job No.
- B21LA23974
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert existing . attached garage into an ADU per attached adu state law.
- Permit Issued
- Issued on 3/9/2022
- Issuing Office
- Current Status
- CofO Issued on 10/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2021 | CARLOS MONTES |
| Corrections Issued | 12/29/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 2/7/2022 | CARLOS MONTES |
| Plan Check Approved | 2/10/2022 | CARLOS MONTES |
| Issued | 3/9/2022 | APPLICANT |
| CofO in Progress | 10/21/2022 | JESUS RODRIGUEZ |
| Permit Finaled | 10/28/2022 | DANIEL ORRANTE |
| CofO Issued | 10/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2022 | DINAH GARIN |
| Sewer availability | Cleared | 1/10/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | DINAH GARIN |
Contact Information
| Architect | Gelfat,, James Evan; Lic. No.: C19847 | 10748 FLAXTON ST CULVER CITY, CA 90230 |
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/1/2022 | Corrections Issued | PATRICK QUALEY |
| Gas Test | 7/1/2022 | Not Ready for Inspection | PATRICK QUALEY |
| PLUMBING-Rough | 7/1/2022 | Corrections Issued | PATRICK QUALEY |
| PLUMBING-Rough | 7/15/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Pre-Inspection | 7/15/2022 | Partial Inspection | PATRICK QUALEY |
| ELECTRICAL-Rough | 7/22/2022 | Corrections Issued | PATRICK QUALEY |
| Gas Test | 7/22/2022 | Not Ready for Inspection | PATRICK QUALEY |
| PLUMBING-Rough | 7/22/2022 | Not Ready for Inspection | PATRICK QUALEY |
| ELECTRICAL-Rough | 7/29/2022 | Approved | JOHNNY MIRANDA |
| Gas Test | 7/29/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 7/29/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 8/3/2022 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/3/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 8/3/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 8/3/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 8/3/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/3/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/3/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/5/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 8/5/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 8/10/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/10/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/12/2022 | Approved | JESUS RODRIGUEZ |
| Final | 9/12/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 9/12/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 9/12/2022 | Approved | JESUS RODRIGUEZ |
| Final | 10/21/2022 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 10/21/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 10/21/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/21/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 10/21/2022 | Approved | JESUS RODRIGUEZ |